112units filed as unsoldInventory · 20 September 2026
30 Nov 2027declared completionMahaRERA registration · read 12 Jul 2026
349registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700076841

Delivery and registration

When is the project declared for completion?

Kohinoor Gardens is registered with MahaRERA as P51700076841 and the promoter has declared completion for 30 Nov 2027.

30 Nov 2027

declared completion

14months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700076841
Registered on28 Jun 2024
Promoter-declared completion30 Nov 2027
Current statusCertificate Signed
Against today14 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Kohinoor Gardens record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Kohinoor Gardens, ₹22.78 Cr of a declared ₹44.19 Cr estimated project cost is reported as incurred, about 51.6%, as at the last certified filing with MahaRERA.

51.6%

₹22.78 Cr

of ₹44.19 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Kohinoor Gardens, 201 of 313 homes filed with MahaRERA are recorded as sold or booked (125 with registered agreements and 76 booked), about 64%, and 112 remain available.

64%sold

201 of 313 homes

₹73.55 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹31.37 Cr (about 43%) is recorded as collected and ₹42.19 Cr as receivable. The project registers 349 homes in total, while this sold/unsold inventory filing covers 313 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 201 registered agreements, the effective carpet rate is ₹8,988/sqft, with eight in ten falling between ₹8,434 and ₹9,318 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 36 owner/investor-held.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 201 homes carry one, and 112 of the 349 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1705375 sqftRs 33.69 lakh typical, over Rs 32.89 lakh to Rs 37.65 lakh16 filed on this stack, floors 1–16

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Kohinoor Gardens, every one of the 112 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 111 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17 and 349 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing B1G+17171-
Wing A1G+17178-

Unit mix on the filing: 349 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ulhasnagar, Shahad station Road, Ulhasnagar, Thane, 421001. Per the filed land record, the plot is bounded to the north by Kohinoor Prime, to the south by adjoining plot, to the east by UMC plot and to the west by 18m DP road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~30 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park30 km
Andheri MIDC / SEEPZ33 km
Chhatrapati Shivaji Int'l Airport35 km
Bandra Kurla Complex (BKC)36 km
Lower Parel / Worli business district44 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

KGI Realty Private Limited is the promoter on 15 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every KGI Realty Private Limited project & its RERA track record →

Other flagged projects by KGI Realty Private Limited

KGI Realty Private Limited
FlaggedThane
KGI Realty Private Limited
FlaggedThane
KGI Realty Private Limited
FlaggedThane
KGI Realty Private Limited
FlaggedThane
KGI Realty Private Limited
FlaggedThane
KGI Realty Private Limited
FlaggedThane

Other RERA-registered projects in Ulhasnagar 1

Golden City
possession by Dec 2026 · Krishna Infra
Regency Antilia Phase Viii Avana
possession by Dec 2026 · Regency Nirman LTD
Mahan Luxuria
possession by Mar 2027 · Kohinoor Builders & Developers
Atlanta Avadh
possession by Apr 2028 · Atlanta Globalprojects LLP
Regency Antilia Phase IX Avana
possession by Apr 2028 · Regency Nirman LTD
Sunrise Towers
possession by Jun 2028 · Matayshree Developers

Major developers building in Ulhasnagar 1

Other RERA-registered projects in Thane

Kohinoor Heights
declared completion Sep 2025 · Kohinoor Buildcon
Kohinoor Highland
possession by Dec 2026 · KGI Realty Private Limited
Kohinoor Imperia
possession by Mar 2030 · KGI Realty Private Limited
Kohinoor Majestic
declared completion Dec 2023 · Sonu Anilkumar Hotchandani
Kohinoor Pearl
possession by Mar 2028 · Real Infra Company
Kohinoor Residency
possession by Dec 2026 · Abrar Haroon Khan

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026