Mumbai/Project record

MahaRERA · the public record

SUNRISE TOWERS

MURBAD ROAD · MATAYSHREE DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

84units filed as unsoldInventory · 20 September 2026
30 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
124registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700079722

Delivery and registration

When is the project declared for completion?

SUNRISE TOWERS is registered with MahaRERA as P51700079722 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700079722
Registered on21 Mar 2025
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUNRISE TOWERS record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In SUNRISE TOWERS, ₹6.76 Cr of a declared ₹24.78 Cr estimated project cost is reported as incurred, about 27.3%, as at the last certified filing with MahaRERA.

27.3%

₹6.76 Cr

of ₹24.78 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SUNRISE TOWERS, 40 of 124 homes filed with MahaRERA are recorded as sold or booked, about 32%, and 84 remain available.

32%sold

40 of 124 homes

₹14.51 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹5.35 Cr (about 37%) is recorded as collected and ₹9.16 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 40 registered agreements, the effective carpet rate is ₹7,871/sqft, with eight in ten falling between ₹7,237 and ₹8,321 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 40 homes carry one, and 84 of the 124 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
FLAT NO. 1002387 sqftRs 30.42 lakh typical, over Rs 26.71 lakh to Rs 34.11 lakh17 filed on this stack, floors 3–13

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SUNRISE TOWERS, every one of the 84 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 83 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 124 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SUNRISE TOWERS WING A1G+15124-

Unit mix on the filing: 124 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MURBAD ROAD, NEAR SHAHAD, Ulhasnagar, Thane, 421001. Per the filed land record, the plot is bounded to the north by HUTS, to the south by MURBAD ROAD, to the east by PIPE LINE and to the west by CENTURY COLONY. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ulhasnagar 1

Golden City
possession by Dec 2026 · Krishna Infra
Regency Antilia Phase Viii Avana
possession by Dec 2026 · Regency Nirman LTD
Mahan Luxuria
possession by Mar 2027 · Kohinoor Builders & Developers
Kohinoor Gardens
possession by Nov 2027 · KGI Realty Private Limited
Atlanta Avadh
possession by Apr 2028 · Atlanta Globalprojects LLP
Regency Antilia Phase IX Avana
possession by Apr 2028 · Regency Nirman LTD

Major developers building in Ulhasnagar 1

Other RERA-registered projects in Thane

Sunrise Vakratund
declared completion Aug 2023 · Sunrise Developers
Sunshine
possession by Dec 2028 · M/S Siddhivinayak Developers
Sunshine Avenue
declared completion Sep 2026 · Shree Ganesh Enterprises
Sunshine Landmark
possession by Dec 2026 · Power Infratech Developers
Sunshine Prasad Chsl
possession by Mar 2030 · Tulsidal Nirman LLP
Sunshine Swapna Nagari
declared completion Dec 2019 · Orchid Housinginfra LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026