MahaRERA Property Intelligence · Palghar

KRISHNA HORIZON - I

P99000008870 · promoter Raj Developers

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP99000008870
Registered on19 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
BUILDING NO 11G+7-
BUILDING NO 0011G+9-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Thane, Thane, 401203. Per the filed land record, the plot is bounded to the north by SURVEY NO 198, to the south by 15 MTR WIDE DP ROAD, to the east by BUILDING NO 1 WING C and to the west by CFC. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ33 km
Powai / Hiranandani business park35 km
Chhatrapati Shivaji Int'l Airport37 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

RAJ Developers is the promoter on 5 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every RAJ Developers project & its RERA track record →

Other flagged projects by RAJ Developers

RAJ Developers
Registration suspendedPalghar

Other RERA-registered projects in Nallasopara West

Rameshwar
possession by Jul 2026 · Chheda Associate
Shalibhadra Yash
possession by Jul 2026 · Sumatinath Builders
Unique Avenue 210
possession by Aug 2026 · Mangalmurti Land Developers
Shree Ganesh Krupa Residency
possession by Sep 2026 · Nutan Construction CO
Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Aleen Heights
possession by Nov 2026 · AB Builders AND Developers

Other RERA-registered projects in Palghar

Krishna Horizon - II
declared completion Sep 2020 · RAJ Developers
Krishna Industrail HUB
possession by Dec 2027 · Shreeji Infra
Krishna Industrial HUB
possession by Dec 2027 · Shreeji Buildcon
Krishna Nagri
declared completion Dec 2025 · Krishna Developers
Krishna Niwas
possession by Apr 2029 · Rajlaxmi Redevelopers
Krishna Residency
possession by Dec 2026 · Rander Corporation Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026