Mumbai/Project record

MahaRERA · the public record

KRISHNA HORIZON - II

Thane · RAJ DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000011696

Delivery and registration

When is the project declared for completion?

KRISHNA HORIZON - II is registered with MahaRERA as P99000011696 and the promoter has declared completion for 30 Sep 2020.

30 Sep 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000011696
Registered on31 Aug 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KRISHNA HORIZON - II record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Suspended / abeyance — the registration is suspended or in abeyance.
  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KRISHNA HORIZON - II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
BULDING NO 11G+10-
BUILDING NO 11G+9-

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for KRISHNA HORIZON - II, with orders passed in 3 of them.

4complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019810426/08/2021Pradeep Panigrahi & 33 Others vs Raj Developerorder passed
CC00600000019908023/02/2022Sana Wasim SHaikh vs Ansari Mohammad Irfanorder passed
CC00600000047997719/04/2024Rushab Nitin Hariya vs Raj Developersorder passed
CC1260251429/04/2026Amit Mehta vs RAJ DEVELOPERSpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2020Due to bank litigation and for reconstitution of partnership firm we required time to complete the project. we have completed almost 59.40% Construction Work and 24.70% Infra Work

Location, Land & Connectivity

Located at Thane, Thane, 401203. Per the filed land record, the plot is bounded to the north by BUILDING NO 6 WING F, to the south by BUILDING NO 6 WING C, to the east by 12MTR WIDE DP ROAD and to the west by GRDEN TO THE WEST. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ33 km
Powai / Hiranandani business park35 km
Chhatrapati Shivaji Int'l Airport37 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

RAJ Developers is the promoter on 5 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every RAJ Developers project & its RERA track record →

Other flagged projects by RAJ Developers

RAJ Developers
Past its declared completion datePalghar

Other RERA-registered projects in Nallasopara West

Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Kunal Height
possession by Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
possession by Dec 2026 · OM Vimal Developers
Anant Tower E AND F
possession by Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
possession by Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · possession by Dec 2026 · Shreeji Associates

Other RERA-registered projects in Palghar

Krishna Industrail HUB
possession by Dec 2027 · Shreeji Infra
Krishna Industrial HUB
possession by Dec 2027 · Shreeji Buildcon
Krishna Niwas
possession by Apr 2029 · Rajlaxmi Redevelopers
Krishna Residency
possession by Dec 2026 · Rander Corporation Limited
Krutartha
declared completion Jun 2025 · M/s Andrades And Company
KT Garden City - Phase III
declared completion Jun 2018 · M/s. Sainagar Development Corporation

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.