Mumbai/Project record

MahaRERA · the public record

KUBER SAMRUDDHI PH-II

Thane · VEER MARUTI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700004552

Delivery and registration

When is the project declared for completion?

KUBER SAMRUDDHI PH-II is registered with MahaRERA as P51700004552 and the promoter has declared completion for 30 Jul 2022.

30 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700004552
Registered on09 Aug 2017
Promoter-declared completion30 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KUBER SAMRUDDHI PH-II record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Veer Maruti Developers is the promoter of record on 94 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

94projects

registered with MahaRERA

14flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KUBER SAMRUDDHI PH-II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
KUBER SAMRUDDHI C WING1G+13-

Legal and disputes

What disputes are disclosed?

9 complaints are on the MahaRERA record for KUBER SAMRUDDHI PH-II, with orders passed in 6 of them.

9complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000101125/10/2018ABHIJEET LAKDE vs Veer Maruti Developersorder passed
CC00600000005747429/12/2018INDRADEV MISHRA vs KUNDAN EKNATH MHATREorder passed
CC00600000007914614/05/2019Sulbha Shridhar Patkar vs Veer Maruti Developersorder passed
CC00600000007915117/05/2019Rashmin Sadanand Bhagat vs Veer Maruti Developersorder passed
CC00600000007915217/05/2019Sudhakar Pandharinath More vs Veer Maruti Developersorder passed
CC00600000009017816/07/2019KISHOR SHEWALE vs KUNDANEKNATH MHATREorder passed
CC1260080312/02/2026GEETA MULEKAR vs VEER MARUTI DEVELOPERSpending / no order on file
CC1260080412/02/2026GEETA MULEKAR vs VEER MARUTI DEVELOPERSpending / no order on file
CC1260080612/02/2026PRASHANT MULEKAR vs VEER MARUTI DEVELOPERSpending / no order on file

Location, Land & Connectivity

Located at Kalyan, Thane, 421202. Per the filed land record, the plot is bounded to the north by S NO -186-1, to the south by GOPINATH KALU-S BUNGLOW, to the east by S NO-186-3 and to the west by S NO-186-6. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park23 km
Andheri MIDC / SEEPZ26 km
Chhatrapati Shivaji Int'l Airport28 km
Bandra Kurla Complex (BKC)30 km
Lower Parel / Worli business district38 km
Nariman Point / Fort44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli West

Amar Elegance
possession by Sep 2026 · Amar Realty
Purva Prime
possession by Sep 2026 · Trimurti Constructions
Anant AND Radhika Heights
possession by Dec 2026 · Ashapura Construction CO
Chintamani Heights & Chintamani Kuber
possession by Dec 2026 · Chintamani Developers
Indira Galaxy
possession by Dec 2026 · Shree Developers
Jai Shree Ganesh Co-Operative Housing Society Limited
possession by Dec 2026 · Shree Vyankatesh Enterprises

Major developers building in Dombivli West

Other RERA-registered projects in Thane

Kuber Samruddhi Phase I
declared completion Dec 2019 · Creative Infra
Kukreja Classic
possession by Apr 2028 · STK Corporation
Kulbansh
declared completion Dec 2021 · Sadguru Krupa Builders AND Developers
Kulswamini
possession by Dec 2026 · Shree SAI Builders
Kulswamini
possession by Dec 2027 · Kulswamini Developers
Kulswamini Avenue
possession by Jun 2027 · Kulswamini Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026