KUKREJA CLASSIC

SANPADA NAVI MUMBAI · STK CORPORATION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700017947

Delivery and registration

When is the project declared for completion?

KUKREJA CLASSIC is registered with MahaRERA as P51700017947 and the promoter has declared completion for 30 Apr 2028.

30 Apr 2028

declared completion

19months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700017947
Registered on28 Sep 2018
Promoter-declared completion30 Apr 2028
Current statusCertificate Signed
Against today19 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KUKREJA CLASSIC record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KUKREJA CLASSIC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
KUKREJA CLASSIC WING A1G+2631 Aug 2022
KUKREJA CLASSIC WING B1G+2631 Oct 2023
KUKREJA CLASSIC WING C1G+2631 Dec 2024
KUKREJA CLASSIC WING D1G+2628 Feb 2026

Legal and disputes

What disputes are disclosed?

16 complaints are on the MahaRERA record for KUKREJA CLASSIC, with orders passed in 4 of them.

16complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250053015/02/2025Dipak Lodha vs STK CORPORATIONpending / no order on file
CC1250061021/02/2025NIteshkumar Jain vs STK CORPORATIONorder passed
CC1250155712/05/2025PRASAD DATTARAM PATIL vs STK CORPORATIONorder passed
CC1250190911/06/2025Narendra Dharampal Rajwanshi vs STK CORPORATIONorder passed
CC1250191311/06/2025Sunil Chandrakant Gade vs STK CORPORATIONorder passed
CC1250277507/08/2025MILIND SUDAM HANDE vs STK CORPORATIONpending / no order on file
CC1250280009/08/2025Amanpreet SUKHBIR RAJPUT vs STK CORPORATIONpending / no order on file
CC1250433907/12/2025swagata maiti maiti vs STK CORPORATIONpending / no order on file
CC1250434008/12/2025subrata rabindranath maiti vs STK CORPORATIONpending / no order on file
CC1260179327/03/2026ALOK VISHWANATH JANA vs STK CORPORATIONpending / no order on file
CC1260192501/04/2026Asit Jana vs STK CORPORATIONpending / no order on file
CC1260273310/05/2026Ujwala SATISH UDARE vs STK CORPORATIONpending / no order on file
CC1260273510/05/2026Chaitanya SATISH UDARE vs STK CORPORATIONpending / no order on file
CC1260273611/05/2026DEEPIKA Anandasayanam PILLAI vs STK CORPORATIONpending / no order on file
CC1260442416/07/2026JOHN JACOB vs STK CORPORATIONpending / no order on file
CC1260445717/07/2026JOHN LONAPPAN JACOB vs STK CORPORATIONpending / no order on file

Location, Land & Connectivity

Located at SANPADA NAVI MUMBAI, PLOT NO. 2 SECTOR 16, Kurla, Mumbai Suburban, 400705. Per the filed land record, the plot is bounded to the north by BHUMIRAJ MONOR, to the south by PROGRESSIVE HEIGHT, to the east by CHOWRANG CHS and to the west by MORAJ RESIDENCY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park12 km
Bandra Kurla Complex (BKC)14 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ16 km
Lower Parel / Worli business district19 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sanpada

ONE Akshar
possession by Dec 2026 · Akshar Realtors
Raheja Solaris-1
possession by Dec 2026 · Raheja Universal Ltd.
BUL BUL CO-Operative Housing Society Limited
possession by Dec 2026 · Ashwiniinfradevelopments Private Limited
Gami Terra
possession by Dec 2026 · LAL Gebi Infra Private Limited
Satyam Altura
possession by Dec 2026 · Satyam Lifescapes LLP
Tricity Montview
possession by Dec 2026 · Tricity Realty LLP

Major developers building in Sanpada

Other RERA-registered projects in Thane

Kulbansh
declared completion Dec 2021 · Sadguru Krupa Builders AND Developers
Kulswamini
possession by Dec 2026 · Shree SAI Builders
Kulswamini
possession by Dec 2027 · Kulswamini Developers
Kulswamini Avenue
possession by Jun 2027 · Kulswamini Builders AND Developers
Kulswamini Brahmand Wing B Janai Shankar
possession by Dec 2030 · Kulswamini Builders & Developers
Kulswamini Pride
possession by Apr 2027 · Kulswamini Buildcon

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026