MahaRERA Property Intelligence · Mumbai Suburban

Kush Sapphire

P51800007193 · Amboli · promoter Kush Buildcon Llp

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800007193
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kush Buildcon Llp is the promoter of record on 40 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Kush Sapphire1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Amboli, Mhatarpada Road, Andheri, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by CTS No 68-A, to the south by CTS No 72-B, to the east by CTS No 68-9 and to the west by CTS No 68-A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park7 km
Bandra Kurla Complex (BKC)8 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kush Buildcon LLP is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Kush Buildcon LLP

Kush Buildcon LLP
FlaggedMumbai Suburban
Kush Buildcon LLP
FlaggedMumbai Suburban
Kush Buildcon LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Andheri West

Hubtown Premiere Residences - Bel Air
possession by Jul 2026 · Hubtown Limited
Morya Grand
possession by Jul 2026 · Nakta Investment Pvt. Ltd.
Umang Heights
possession by Aug 2026 · L K Infracon LLP
Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Kush Solitaire
declared completion Dec 2023 · Kush Buildcon LLP
Kush Symphony
declared completion Jun 2025 · Kush Buildcon LLP
Kyron
possession by Dec 2028 · Zire Rushi Construction
L&T Realty Harmony
possession by Aug 2028 · Elevated Avenue Realty LLP
La Alteza
possession by Dec 2026 · Emerald Developers
La Charmaine Chsl
declared completion Dec 2025 · JDN Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026