MahaRERA Property Intelligence · Raigarh
P52000017801 · PALI SUDHAGAD · promoter Sadanand Laxmanrao Patil
| MahaRERA registration | P52000017801 |
| Registered on | 17 Sep 2018 |
| Promoter-declared completion | 30 Jun 2022 |
| Current status | Certificate Signed |
| Against today | about 49 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Sadanand Laxmanrao Patil is the promoter of record on 20 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| C1 | 1 | G+0 | 30 Dec 2021 |
| C2 AND C3 | 1 | G+0 | 30 Dec 2021 |
| C4 AND C5 | 1 | G+0 | 30 Dec 2021 |
| C6 AND C7 | 1 | G+0 | 30 Dec 2021 |
| C8 AND C9 | 1 | G+0 | 30 Dec 2021 |
| C10 AND C11 | 1 | G+0 | 30 Dec 2021 |
| C12 AND C13 | 1 | G+0 | 30 Dec 2021 |
| C14 AND C15 | 1 | G+0 | 30 Dec 2021 |
| C16 AND C17 | 1 | G+0 | 30 Dec 2021 |
| C18 AND C19 | 1 | G+0 | 30 Dec 2021 |
| C20 AND C21 | 1 | G+0 | 30 Dec 2021 |
| C22 AND C23 | 1 | G+0 | 30 Dec 2021 |
| C27 | 1 | G+0 | 30 Dec 2021 |
| C28 | 1 | G+0 | 30 Dec 2021 |
| C29 | 1 | G+0 | 30 Dec 2021 |
| C30 | 1 | G+0 | 30 Dec 2021 |
| C31 | 1 | G+0 | 30 Dec 2021 |
| C32 | 1 | G+0 | 30 Dec 2021 |
| C33 | 1 | G+0 | 30 Dec 2021 |
| C34 | 1 | G+0 | 30 Dec 2021 |
| B14 AND B15 | 1 | G+1 | 30 Dec 2021 |
| B16 AND B17 | 1 | G+1 | 30 Dec 2021 |
| B18 AND B19 | 1 | G+1 | 30 Dec 2021 |
| B20 | 1 | G+1 | 30 Dec 2021 |
| B29 AND B30 | 1 | G+1 | 30 Dec 2021 |
| B31 AND B32 | 1 | G+1 | 30 Dec 2021 |
| B33 AND B34 | 1 | G+1 | 30 Dec 2021 |
| B35 AND B36 | 1 | G+1 | 30 Dec 2021 |
| B37 AND B38 | 1 | G+1 | 30 Dec 2021 |
| B39 AND B40 | 1 | G+1 | 30 Dec 2021 |
| B41 AND B42 | 1 | G+1 | 30 Dec 2021 |
| B43 AND B44 | 1 | G+1 | 30 Dec 2021 |
| B45 AND B46 | 1 | G+1 | 30 Dec 2021 |
| B47 AND B48 | 1 | G+1 | 30 Dec 2021 |
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
Located at PALI SUDHAGAD, KHOPOLI PALI ROAD, Haveli, Pune, 410205. Per the filed land record, the plot is bounded to the north by KHOPOLI PALI ROAD, to the south by SURVEY NO 64 PART OF MAUJE BHILPADA, to the east by SURVEY NO 61 AND 63 OF MAUJE BHILPADA and to the west by SURVEY NO 67 PART 72 PART OF MAUJE BHILPADA ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~110 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Nariman Point / Fort | 107 km |
| Powai / Hiranandani business park | 110 km |
| Lower Parel / Worli business district | 110 km |
| Bandra Kurla Complex (BKC) | 110 km |
| Chhatrapati Shivaji Int'l Airport | 112 km |
| Andheri MIDC / SEEPZ | 114 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in LAKE CITY PHASE-2?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Sadanand Laxmanrao Patil is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026