0units filed as unsoldInventory · 19 July 2026
30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
20registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800026325

Delivery and registration

When is the project declared for completion?

LAXMI ANNEX is registered with MahaRERA as P51800026325 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800026325
Registered on08 Sep 2020
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LAXMI ANNEX record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Laxmidevi Developers is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In LAXMI ANNEX, 15 of 15 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

15 of 15 homes

₹13.19 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹12.92 Cr (about 98%) is recorded as collected and ₹26.37 Lakh as receivable. The project registers 20 homes in total, while this sold/unsold inventory filing covers 15 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 15 registered agreements, the effective carpet rate is ₹19,230/sqft, with eight in ten falling between ₹12,980 and ₹25,941 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 5 not for sale.

What the filings record, home by home

Read from MahaRERA on 19 July 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 15 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in LAXMI ANNEX is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 15 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 15 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 20 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
LAXMI ANNEX1G+122031 Dec 2022

Unit mix on the filing: 20 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JAWAHAR NAGAR GOREGAON WEST, ROAD NO 16, Borivali, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by PLOT NO 299, to the south by PLOT NO 301, to the east by ROAD NO 16 PLOT NO 304 and to the west by PLOT NO 285 ROAD NO 3. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Laxmidevi Developers is the promoter on 7 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Laxmidevi Developers

Laxmidevi Developers
FlaggedMumbai Suburban
Laxmidevi Developers
FlaggedMumbai Suburban
Laxmidevi Developers
FlaggedMumbai Suburban
Laxmidevi Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Goregaon West

Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Sahakar Revanta
possession by Sep 2026 · Sahakar Builders & Developers
Vallabh Krupa Chsl
possession by Oct 2026 · Gun Rajan Constructions
Siddharth Nagar Gulmohar CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Paschim Jagruti CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Swami Vivekanand Chsl
possession by Dec 2026 · Dhariwal Developers Private Limited

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Laxmi Eternity
declared completion Dec 2023 · Shree Ashapura Laxmidevi Developers
Laxmi Heights
declared completion Dec 2018 · Laxmidevi Developers
Laxmi Heights
declared completion Jun 2025 · Pankajkumar & Co.
Laxmi Nagar
possession by Dec 2026 · Reliable Constructions
Laxmi Palace Chsl
possession by Dec 2028 · Prime Civil Infrastructures Private Limi
Laxmi Sanskruti
declared completion Feb 2024 · Laxmidevi Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026