Mumbai/Project record

MahaRERA · the public record

LE PALAZZO

NANA CHOWK · Sri Harsh Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Aug 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012304

Delivery and registration

When is the project declared for completion?

LE PALAZZO is registered with MahaRERA as P51900012304 and the promoter has declared completion for 31 Aug 2026.

31 Aug 2026

declared completion

1months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012304
Registered on01 Sep 2017
Promoter-declared completion31 Aug 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LE PALAZZO record 29 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Suspended / abeyance — the registration is suspended or in abeyance.
  • Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sri Harsh Developers is the promoter of record on 83 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

83projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LE PALAZZO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+43.

BuildingWingsFloorsDeclared completion
LE PALAZZO1G+43-

Legal and disputes

What disputes are disclosed?

15 complaints are on the MahaRERA record for LE PALAZZO, with orders passed in 14 of them.

15complaints

14with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001208827/11/2017Mr koimavalappil v madhusudhan and Mrs koimavalappil m harsha vs SRI HARSH DEVELOPERSorder passed
CC00600000005738520/12/2018JITENDRA KANTILAL SHAH AND OTHERS vs SRI HARSH DEVELOPERSorder passed
CC00600000011065423/08/2019Shah Investments vs Sri Harsh Developersorder passed
CC00600000011065223/08/2019Usha Metal Works vs Sri Harsh Developersorder passed
CC00600000011065323/08/2019Usha Metal Works vs Sri Harsh Developersorder passed
CC00600000019707025/05/2021Pinakin Laxmichand Shah vs Sri Harsh Developersorder passed
CC00600000019706925/05/2021Shailesh Kantilal Shah vs Sri Harsh Developersorder passed
CC00600000019708226/05/2021Shailesh Kantilal Shah vs Sri Harsh Developersorder passed
CC00600000019708526/05/2021Zeni Shailesh Shah vs Sri Harsh Developersorder passed
CC00600000019707225/05/2021Ankur J. Shah HUF through Karta Ankur Jitendra Shah vs Sri Harsh Developersorder passed
CC00600000019708426/05/2021Ramesh Kantibhai Patani vs Sri Harsh Developersorder passed
CC00600000019788309/09/2021Sanjana Cryogenic Storages Limited vs Sri Harsh Developersorder passed
CC00600000019826706/09/2021Manju Ramesh Vardhan vs Sri Harsh Developersorder passed
CC00600000019836218/09/2021Meenakshi Nitin Shah vs Sri Harsh Developersorder passed
CC00600000047992504/04/2024Mrs. Manju Ramesh Vardhan vs Sri Harsh Developerspending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Aug 2024This project is developed under 33(7) MHADA Scheme. And due to tenants legal and technical issues we couldn't complete the project and obtain O.C.
31 Aug 202431 Aug 2026We required extension till 28.08.2026, due to various reasons and all the reasons are attached in the document upload tab

Location, Land & Connectivity

Located at NANA CHOWK, A.K MARG ROAD, Ward ABCD, Mumbai City, 400036. Per the filed land record, the plot is bounded to the north by AUGUST KRANTI MARG, to the south by C S NO 2 519, to the east by 40 WIDE DP ROAD KNOWN AS PAPANASWADI ROAD and to the west by C S NO 9 519. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nana Chowk

Sanjana Heights
possession by Dec 2026 · Safeway Projects Private Limited
Terraces Forjett Hill
possession by Sep 2027 · Suparshva Incorporation
Sesen
possession by Dec 2027 · Sesen Realty PVT LTD
Lifescapes Altimo
declared completion Mar 2024 · Peccadily Estate Pvt Ltd

Other RERA-registered projects in Mumbai City

Leela Laher
declared completion Dec 2023 · Bineeta
Lifescapes Altimo
declared completion Mar 2024 · Peccadily Estate Pvt Ltd
Lifescapes Glory
possession by Jun 2027 · Om Shanti Developers
Lifescapes Kshitij
possession by Nov 2026 · Roxina Real Estate Pvt. Ltd.
Lifescapes Siddhant
declared completion Jul 2025 · Meridian Construction Pvt. Ltd.
Link Plaza
declared completion Dec 2019 · Ghansham Properties

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026