MahaRERA Property Intelligence · Mumbai Suburban

LUMA TOWERS A & B

P51800012155 · Andheri · promoter Ecc-Konark Joint Venture

Certificate SignedDue 30 Jun 2026

Delivery & Registration

MahaRERA registrationP51800012155
Registered on01 Sep 2017
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ecc-Konark Joint Venture is the promoter of record on 54 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~62.0% of the estimated project cost incurred as of the last certificate (₹85.22 Cr spent against a ₹137.55 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~62.0% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 129 homes filed with MahaRERA, 120 are sold/booked (89 with registered agreements + 31 booked) and 9 remain available (~93% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹254.37 Cr in agreement value so far. Of that, ₹196.14 Cr (~77%) is already collected, ₹58.22 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 120 registered agreements, the effective carpet rate is ₹26,095/sqft (typical range ₹18,177–₹30,120) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1102983 sqft (91.36 sqm)₹1.11 Cr
Floor 2203577 sqft (53.65 sqm)₹65.12 Lakh
Floor 2204983 sqft (91.36 sqm)₹1.11 Cr
Floor 3304983 sqft (91.36 sqm)₹1.11 Cr
Floor 4404983 sqft (91.36 sqm)₹1.11 Cr
Floor 6604983 sqft (91.36 sqm)₹1.16 Cr
Floor 7704983 sqft (91.36 sqm)₹1.16 Cr
Ground/Floor 0GR-01983 sqft (91.36 sqm)₹1.11 Cr
Ground/Floor 0GR-04869 sqft (80.77 sqm)₹98.03 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18 and 129 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Luma Tower A1G+1866-
Luma Tower B1G+1863-

Unit mix on the filing: 129 residential.

Complaints & Orders

16 complaints are on the MahaRERA record for this project, with orders passed in 12. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000049716/09/2017KEZER ABBAS KHARAWALA vs ECC-DB- JOINT VENTUREorder passed
CC00600000000044111/09/2017shyam shirke swati shirke vs ECC DB JVorder passed
CC00600000005523905/07/2018Mr. Sahil Rana vs M/S Eversmile Construction Pvt Ltd.order passed
CC00600000010023225/07/2019Mr. Sahil Rana vs M/s. Eversmile Construction Co. Pvt. Ltdorder passed
CC00600000005598428/08/2018KEZER A. KHARAWALA vs ECC-DB JOINT VENTUREorder passed
CC00600000019543129/12/2020(1) SAURABH RUNGTA AND (2) NEHA RUNGTA vs 1. EVERSMILE CONSTRUCTION COMPANY PVT. LTD.; 2. DB REALTY LTD.; 3. KONARK CONWELL LLP; 4. ECC DB JVorder passed
CC00600000019543415/01/20211.Abhishek Rungta; 2. Usha Rungta; 3. Vinod Kumar Rungta; 4. Priyanka Kejriwal/Rungta vs 1. EVERSMILE CONSTRUCTION COMPANY PVT. LTD.; 2. DB REALTY LTD.; 3. KONARK CONWELL LLP; 4. ECC DB JVorder passed
CC00600000019543829/12/20201. VIKAS LATH AND 2. VINOD KUMAR LATH vs 1. EVERSMILE CONSTRUCTION COMPANY PVT. LTD.; 2. DB REALTY LTD.; 3. KONARK CONWELL LLP; 4. ECC DB JVorder passed
CC00600000019544029/12/20201. MANISH LATH AND 2. MAYA DEVI LATH vs 1. EVERSMILE CONSTRUCTION COMPANY PVT. LTD.; 2. DB REALTY LTD.; 3. KONARK CONWELL LLP; 4. ECC DB JVorder passed
CC00600000019660202/04/2021VINEET RUNGTA & MUKTA RUNGTA vs 1. EVERSMILE CONSTRUCTION COMPANY PVT. LTD.; 2. DB REALTY LIMITED; 3. KONARK CONWELL LLP;4.ECC DB JVorder passed
CC00600000019274426/02/2020KEZER ABBAS KHARAWALA vs ECC-DB JOINT VENTUREorder passed
CC00600000028214129/07/2022RAMESHCHAND B JAIN vs M/s. ECC-DB JOINT VENTUREorder passed
CC1260086016/02/2026Kamats Holiday Resorts Silvasa Limited vs ECC-KONARK JOINT VENTUREpending / no order on file
CC1260086416/02/2026Vikram Vithal Kamat vs ECC-KONARK JOINT VENTUREpending / no order on file
CC1260373717/06/2026RAJ MERCHANT ABRAHAM vs ECC-KONARK JOINT VENTUREpending / no order on file
CC1260385922/06/2026ALPA DILIP PATEL vs ECC-KONARK JOINT VENTUREpending / no order on file

Legal & Litigation

The promoter has declared 17 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court BombayAO No 118 of 20102010Disposed
City Civil CourtCivil Suit No 1558 of 20112011Cra Admitted
High Court BombayWP No 2294 of 20022002Matter Kept For Final Hearing And Final Disposal
High Power Committee SraAppeal No 174 of 20162016Matter Closed For Orders
High Court BombayWP No 3011 of 20022002Matter Kept For Production
High Court BombayCRA No 23 of 20142014Ongoing
City Civil CourtSuit No 1782 of 20062006Ongoing
Debt Recovery TribunalApplication No 170 of 20202020Ongoing
Apex Grievance Redressal CommitteeAppeal No 32 of 20232023Dismissed
Apex Grievance Redressal CommitteeAppeal No 41 of 20232023Dismissed
Apex Grievance Redressal CommitteeAppeal No 110 of 20232023Disposed
Additional Collector And Competent Authority WsAppeal No 1005 of 20232023Ongoing
Additional Collector And Competent Authority WsAppeal No 1004 of 20232023Ongoing
Apex Grievance Redressal CommitteeAppeal No of 20232023Ongoing
High Court BombayCivil Writ Petition L-No 9609 of 20232023Disposed
High Court BombayWrit Petition L-No 19898 of 20232023Ongoing
City Civil Court At Dindoshi, Goregaon15582011Ongoing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202531 Dec 2025A. We, the Promoter, registered the captioned Project with RERA in the September, 2017, bearing No. P51800012155 with specific Project Information inter-alia Project Completion dat
30 Dec 202330 Jun 2026Following are the reasons for slight delay in construction works of the Project known as ‘Luma Towers A & B’ (“Project”): a. ECC-Konark Joint Venture (“Promoter”) holds the RERA Re

Location, Land & Connectivity

Located at Andheri, Sahar Road, Borivali, Mumbai Suburban, 400059. Per the filed land record, the plot is bounded to the north by CTS 9, to the south by Approx 13 mtr wide DP Road, to the east by Internal Road and to the west by CTS 40 1C. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Andheri MIDC / SEEPZ3 km
Powai / Hiranandani business park4 km
Bandra Kurla Complex (BKC)4 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

ECC-Konark Joint Venture is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by ECC-Konark Joint Venture

ECC-Konark Joint Venture
FlaggedMumbai Suburban

Other RERA-registered projects in Andheri East

Royal Green
possession by Dec 2026 · Admire Revive Builder & Developer
VKG Estates
possession by Dec 2026 · Greenery Rock LLP
59 Avenue
possession by Dec 2026 · M/s Ganesh Vishal Infra Engineering Priv
Gateway Residences
possession by Dec 2026 · Infinity Narayani Associates
LA Grace
possession by Dec 2026 · Ecohomes Ventures
Park Royale Phase III
possession by Dec 2026 · Shivranjani Properties LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Luminaara
possession by Dec 2029 · NVK Real Estate Private Limited
Luminaire Gold
declared completion Dec 2022 · Yash Development
Luxury Chsl LTD
declared completion Jun 2025 · Laxmidevi Developers
M K Chamber
declared completion Dec 2024 · Shaista Majid Khan
M.K Heritage
possession by Dec 2026 · Shaista Majid Khan
M K Residency
possession by Dec 2028 · Shaista Majid Khan

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026