Mumbai/Project record

MahaRERA · the public record

Maimuna apartment

Village kalina · Salim Amin Behlim

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800016654

Delivery and registration

When is the project declared for completion?

Maimuna apartment is registered with MahaRERA as P51800016654 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800016654
Registered on05 Jun 2018
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Maimuna apartment record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Maimuna apartment in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Maimuna Apartment1G+625 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2020To, Maharashtra Real Estate Regulatory Authority 3 rd Floor, A-Wing, Slum Rehabilitation Authority, Administrative Building , Anant Kanekar Marg, Bandra(E), Mumbai-400051
31 Jul 202031 Jul 2023There is some delay in the completion of our project due to the harsh impact of Covid 19 on the real estate sector. The second wave has caused a lot of stress and trouble as our la

Location, Land & Connectivity

Located at Village kalina, Gaothan road, Andheri, Mumbai Suburban, 400029. Per the filed land record, the plot is bounded to the north by Gaothan lane, to the south by Gaothan lane, to the east by CTS No 6270 and gaothan road and to the west by Gaothan lane. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz East

Sana Enclave
possession by Sep 2027 · Sana Enterpises
ZAS-9
possession by Dec 2027 · ZAS Homes
Supreme Ellora
possession by Oct 2028 · Supreme Realtors
D Solitaire
declared completion Jun 2026 · Krishnan AND Kamal Associates
Almeida Avana
declared completion Dec 2024 · D' Almeida Developers
Louis Apartments
Past its declared completion date · declared completion Dec 2022 · City Heights Developers

Other RERA-registered projects in Mumbai Suburban

Mairav Jayesh
possession by Nov 2028 · Krypton Buildtech LLP
Maithili Residency Phase-1
possession by Dec 2027 · Global Oricon Developers
Maithili Residency Phase-2
possession by Dec 2027 · Global Oricon Developers
Maitri Enclave
possession by Dec 2026 · Atharva Enterprises
Maitri Siya Heights
possession by Dec 2030 · Maitri Siya Enterprises
Maitri Vijay Co-Operative Housing Society Limited - Phase I
declared completion Jun 2023 · Mishal Construction Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026