MahaRERA Property Intelligence · Mumbai Suburban

MANALI CHS LTD

P51800009091 · promoter Sainath Builders And

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP51800009091
Registered on19 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sainath Builders And is the promoter of record on 33 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
MANALI CHS LTD1G+16-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005564409/08/2018MANASI PRASHANT GORE vs SAINATH BUILDERS AND DEVELOPERSorder passed
CC00600000005797206/02/2019Vinod Manohar Gaikwad vs Sainath Builders And Developersorder passed

Legal & Litigation

The promoter has declared 8 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High CourtCOMS/468/20162016Pre Admission
Bombay High CourtWPL/1754/20172017Pre Admission
Bombay City Civil Court2480/20142014Suit Stayed
Bombay City Civil Court994/20172017Directions
Bombay City Civil Court995/20172017Directions
Bombay City Civil Court1011/20172017Directions
Shindewadi Court4228241/SS/20162016Not Heard Case
Arbitration12015Arguments

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202230 Sep 2021The Promoter states that the entire building of 15 floors is ready and in all prospects is ready. Because of Covid situation we could not process the application for consumption ad

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by ONGC Building, to the south by Manisha Tower, to the east by Eastern Express Highway and to the west by D P Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund East

Abundance
possession by Sep 2026 · Goodwill Developers
Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

Manas
declared completion Dec 2023 · Sstc India Constructions
Manas Rangoli Residency
declared completion Mar 2024 · Rangoli Developers
Manasarovar
declared completion Mar 2026 · Harasiddh Projects
Mandlik Nagar CHS LTD Phase II Rehab Wing E PT AND F
declared completion Dec 2018 · Triumph Builders LLP
Mandor Bliss
possession by Dec 2028 · Mandor Home Villa LLP
Mandor Heights Phase-II
declared completion Mar 2023 · A S K Construction Co

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026