MahaRERA · the public record
MANGAL VILLA C.H.S
MANGAL VILLA CO.OP HOUSING SOCIETY BADLAPUR · SHREE SAI ENTERPRISES
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
01 Sep 2024
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700028805
Delivery and registration
When is the project declared for completion?
MANGAL VILLA C.H.S is registered with MahaRERA as P51700028805 and the promoter has declared completion for 01 Sep 2024.
01 Sep 2024
declared completion
24months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700028805 |
| Registered on | 30 Mar 2021 |
| Promoter-declared completion | 01 Sep 2024 |
| Current status | Certificate Signed |
| Against today | about 24 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MANGAL VILLA C.H.S record 15 quarterly progress reports since registration.
15quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for MANGAL VILLA C.H.S in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| MANGAL VILLA CHS | 1 | G+4 | 02 Mar 2022 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 01 Sep 2023 | Project Construction is 100% Completed and applied for OC. But the OC Process is going on and OC will be Recieved. For Safer Side we want Extention of RERA Certificate till 01-09-2 |
| 01 Sep 2023 | 01 Sep 2024 | Project is Alomost Complited and applied for Completion Certificate it is under Process. Therfore we here by request You to give or Grant Extention of minimum of One Year on safer |
Location, Land & Connectivity
Located at MANGAL VILLA CO.OP HOUSING SOCIETY BADLAPUR, OPP WATER SUPPLY OFFICE, BELAVALI, BADLAPUR, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by LAND S NO 27 A OR 4 OR 1, to the south by LAND S NO 27 A OR 4 OR 3, to the east by LAND BEARING ROAD and to the west by LAND BEARING NALLA. These are the boundaries as recorded in the filed land record.