MahaRERA Property Intelligence · Raigarh

MAPLE IVY

P52000015717 · ULWE · promoter Pankti Jignesh Goradia

Certificate SignedDue 31 Dec 2022

Delivery & Registration

MahaRERA registrationP52000015717
Registered on19 Mar 2018
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pankti Jignesh Goradia is the promoter of record on 3 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 3 homes filed with MahaRERA, 3 are sold/booked and 0 remain available (~100% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹4 in agreement value so far. Of that, ₹2 (~50%) is already collected, ₹2 receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 3 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
MAPLE IVY WING B1G+16331 Dec 2022

Unit mix on the filing: 2 residential and 1 non-residential (shops/offices).

Complaints & Orders

9 complaints are on the MahaRERA record for this project, with orders passed in 9. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000039746429/09/2023Rajesh Ramkelkar vs Pankti Jignesh Goradiaorder passed
CC00600000042947429/02/2024Dharamraj Maple IVY B WING CHS LTD. (society) vs Yushan Realty Venturesorder passed
CC1240038410/10/2024PANKTI JIGNESH GORADIA vs Reena P Kurilorder passed
CC1240023025/09/2024PANKTI JIGNESH GORADIA vs Balwant Singhorder passed
CC1250206524/06/2025PANKTI JIGNESH GORADIA vs Bhaktivinayakam Arulorder passed
CC1250206624/06/2025PANKTI JIGNESH GORADIA vs Petchi muthu Arulorder passed
CC1250206724/06/2025PANKTI JIGNESH GORADIA vs Ashok Mahavir Shivhareorder passed
CC1250207425/06/2025PANKTI JIGNESH GORADIA vs Amandeep Singhorder passed
CC1250207725/06/2025PANKTI JIGNESH GORADIA vs Arpit Harinkhereorder passed

A co-operative housing society is the complainant here (Dharamraj Maple IVY B WING CHS LTD.) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202231 Dec 2022Considerable time is lost in covid 19 pandemic and shortage of labor and multiple lockdowns added to the delay. work at project site is however going on smoothly and we are sure of

Location, Land & Connectivity

Located at ULWE, SECTOR 09, Panvel, Raigarh, 400707. Per the filed land record, the plot is bounded to the north by PLOT NO 96, to the south by 30 MTR WIDE ROAD, to the east by NATURAL POND and to the west by 15 MTR WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort18 km
Lower Parel / Worli business district21 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport26 km
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dronagiri

Pramukh Dharma
possession by Sep 2026 · Pramukh Associates
Vaastu Ankita
possession by Sep 2026 · Vaastu Builders & Developers
OM Shakti Enclave
possession by Dec 2026 · OM Shakti Enterprises
Vaishnavi Emperia
possession by Nov 2027 · RK Group OF Infra
Villa Oceano
declared completion Dec 2025 · Shreeji Creations
Lakhani Grandeur
declared completion Oct 2025 · Lakhani Builders PVT LTD

Other RERA-registered projects in Raigarh

Maple ONE
declared completion Jun 2025 · Bhoomi & Dharti Associates
Maple Villa
declared completion Dec 2017 · Avachar Beachara Bhathi
Marathon Nexzone Acrux -1
declared completion Dec 2021 · Sanvo Resorts Pvt. Ltd.
Marathon Nexzone Acrux -2
declared completion Dec 2023 · Sanvo Resorts Pvt. Ltd.
Marathon Nexzone Altis -1
declared completion Dec 2019 · Sanvo Resorts Pvt. Ltd.
Marathon Nexzone Altis -2
declared completion Dec 2022 · Sanvo Resorts Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.