Mumbai/Project record

MahaRERA · the public record

Maplle Plazza

JOGESHWARI EAST · Maplle Infraprojects Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002879

Delivery and registration

When is the project declared for completion?

Maplle Plazza is registered with MahaRERA as P51800002879 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002879
Registered on04 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Maplle Plazza record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Maplle Infraprojects Limited is the promoter of record on 75 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

75projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Maplle Plazza in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Maplle Plazza1G+12-
NA1--

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Maplle Plazza, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019840721/09/2021Jitendra Shah vs M/s. Maplle Infraprojects Limited (Formerly known as Maple Industries (Laminates)limited.order passed
CC00600000019840921/09/2021Chandravali Jitendra Shah vs M/s. Maplle Infraprojects Limited (Formerly known as Maple Industries (Laminates) Limited.order passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay City Civil Court At Dindoshi14622016Service Of Notice Of Motion And Suit To Defendant Pending
Bombay City Civil Court At Dindoshi18722018Reply On Chamber Summons

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2022In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B.
30 Sep 202230 Mar 2023In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas
30 Mar 202331 Dec 2023In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r
31 Dec 202331 Dec 2025I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52100025883. As per HEARING DATED 10th December 2024, Hon'ble Shri Man

Location, Land & Connectivity

Located at JOGESHWARI EAST, SUBHASH NAGAR, Andheri, Mumbai Suburban, 400060. Per the filed land record, the plot is bounded to the north by CTS 250, to the south by CTS 264 being part of Proposed DP Road, to the east by Existing Subhash Road and to the west by CTS 253. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)5 km
Andheri MIDC / SEEPZ5 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district11 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari East

Prem Builders
possession by Oct 2026 · Prem Builders
Aim Heritage
possession by Dec 2026 · M/s Aim Realtors Private Limited
AIM Paradise
possession by Dec 2026 · S.k. Enterprises
Avant Heritage - III
possession by Dec 2026 · Avant Heritage III Realty Pvt. Ltd.
Devbhoomi
possession by Dec 2026 · Metro Capital
Iifl Centre
Developer in insolvency (NCLT) · possession by Dec 2026 · Spenta Sun City Private Limited

Major developers building in Jogeshwari East

Other RERA-registered projects in Mumbai Suburban

Marathon Eminence
declared completion Dec 2023 · Nexzone Buildcon LLP
Marathon Millennium 2
declared completion Jun 2026 · Terrapolis Assets PVT LTD
Marathon Monte Carlo 3
possession by Dec 2026 · Marathon Realty PVT LTD
Marathon Neopark Ashoka Wing A
declared completion Dec 2025 · Marathon Nextgen Realty LTD
Marathon Neopark Ashoka Wing B
declared completion Dec 2025 · Marathon Nextgen Realty LTD
Marathon Neopark Ashoka Wing C
possession by Jun 2028 · Marathon Nextgen Realty LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026