MahaRERA Property Intelligence · Mumbai Suburban
P51800018106 · BHANDUP WEST · promoter Suyog Developers
| MahaRERA registration | P51800018106 |
| Registered on | 10 Oct 2018 |
| Promoter-declared completion | 31 Dec 2024 |
| Current status | Certificate Signed |
| Against today | about 19 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Suyog Developers is the promoter of record on 36 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| MARATHON NEOSKIES 1 | 1 | G+23 | - |
40 complaints are on the MahaRERA record for this project, with orders passed in 40. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000428786 | 09/01/2024 | Diptesh Satyawan Kande vs Mayur shah | order passed |
| CC006000000439702 | 30/05/2024 | Shashank Prabhakar Chavan vs M/S, Suyog Developers | order passed |
| CC006000000500645 | 31/05/2024 | Sonal Shashank Chavan vs M/S Suyog Developers | order passed |
| CC12400730 | 11/11/2024 | AMIT VIJAY PAWAR vs M/S Suyog Developers | order passed |
| CC12400750 | 12/11/2024 | GANESH BABAN PAWAR vs M/S Suyog Developers | order passed |
| CC12400833 | 20/11/2024 | SHRADDHA VIJAY KANDE vs M/S Suyog Developers | order passed |
| CC12400840 | 21/11/2024 | POONAM SUKUR BHOIR vs M/S Suyog Developers | order passed |
| CC12400845 | 21/11/2024 | MILIND MINANATH PARADKAR vs M/S Suyog Developers | order passed |
| CC12400854 | 22/11/2024 | KALYANI RAHUL CHALKE vs M/S Suyog Developers | order passed |
| CC12400856 | 23/11/2024 | Prasad Mahadev Bamane vs M/S Suyog Developers | order passed |
| CC12400876 | 23/11/2024 | Amol Mahadev Sawant vs M/S Suyog Developers | order passed |
| CC12400879 | 24/11/2024 | ROHAN TUKARAM PANGALE vs M/S Suyog Developers | order passed |
| CC12400891 | 26/11/2024 | Akshay Sushilkumar Bartakke vs M/S Suyog Developers | order passed |
| CC12400894 | 26/11/2024 | Sachin Gunaji Dawal vs M/S Suyog Developers | order passed |
| CC12400902 | 27/11/2024 | Seema Vikrant Patil vs M/S Suyog Developers | order passed |
| CC12400906 | 27/11/2024 | Kishor Subhash Shirsat vs M/S Suyog Developers | order passed |
| CC12400933 | 29/11/2024 | Sandeep Ramchandra Sawant vs M/S Suyog Developers | order passed |
| CC12400940 | 30/11/2024 | ARCHIE SAHADEV CHAUGHULE vs M/S Suyog Developers | order passed |
| CC12400944 | 30/11/2024 | Purushottam Ravindra Sawant vs M/S Suyog Developers | order passed |
| CC12400976 | 02/12/2024 | Mangesh Janardan Bandekar vs M/S Suyog Developers | order passed |
| CC12401075 | 09/12/2024 | Supriya Vijay Sawant vs M/S Suyog Developers | order passed |
| CC12401076 | 09/12/2024 | ANURADHA ARVIND INGALE vs M/S Suyog Developers | order passed |
| CC12401079 | 10/12/2024 | Pallavi Kunjar Tirmare vs M/S Suyog Developers | order passed |
| CC12401108 | 12/12/2024 | Prashant Dewoo Tambe vs M/S Suyog Developers | order passed |
| CC12401120 | 13/12/2024 | Rohan Ramchandra Jadhav vs M/S Suyog Developers | order passed |
| CC12401166 | 18/12/2024 | ARATI NAMDEO KANADE vs M/S Suyog Developers | order passed |
| CC12401157 | 17/12/2024 | Santosh Anant Palvankar vs M/S Suyog Developers | order passed |
| CC12401173 | 18/12/2024 | Sidhesh Vijaykumar Pawar vs M/S Suyog Developers | order passed |
| CC12401196 | 21/12/2024 | Suraj Sudhakar Talkar vs M/S Suyog Developers | order passed |
| CC12401201 | 21/12/2024 | Sanjay Digambar Parab vs M/S Suyog Developers | order passed |
| CC12401278 | 29/12/2024 | KARUNA SUBHASH POTE vs M/S Suyog Developers | order passed |
| CC12401284 | 30/12/2024 | Suraj Shrirang Gole vs M/S Suyog Developers | order passed |
| CC12500364 | 03/02/2025 | Seema Suryakant Shinde vs M/S Suyog Developers | order passed |
| CC12500691 | 27/02/2025 | Mayur Prakash Raut vs M/S Suyog Developers | order passed |
| CC12500766 | 06/03/2025 | Pooja Ratnakar Sawant vs M/S Suyog Developers | order passed |
| CC12500832 | 11/03/2025 | Varada Rajmohan Pillai vs M/S Suyog Developers | order passed |
| CC12500989 | 21/03/2025 | Sheetal Sachin Bhatose vs M/S Suyog Developers | order passed |
| CC12501022 | 26/03/2025 | Rushikesh Anant Salunke vs M/S Suyog Developers | order passed |
| CC12503807 | 31/10/2025 | M/S Suyog Developers vs Sandeep Bhausaheb Dighe | order passed |
| CC12503808 | 31/10/2025 | M/S Suyog Developers vs Sunil Sharad Vinekar | order passed |
The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay City Civil Court | 6259 | 2018 | Pending For Final Hearing |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Dec 2023 | 31 Dec 2024 | due to delay in approval by authority along with acute shortage of construction Water Supply and other construction raw material |
Located at BHANDUP WEST , UTTKARSH NAGAR , Kurla, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by CTS NO 28 ADJOINING SLUM, to the south by CTS NO 192 ADJOINING SLUM, to the east by CTS NO 31 32 ADJOINING JEEVAN ANAND BLDG and to the west by CTS NO 01 ADJOINING SLUM. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in MARATHON NEOSKIES?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026