Mumbai/Project record

MahaRERA · the public record

MEDINEE NIKETAN

BAMANWADA · SS ENTERPRISE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800017639

Delivery and registration

When is the project declared for completion?

MEDINEE NIKETAN is registered with MahaRERA as P51800017639 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800017639
Registered on29 Aug 2018
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MEDINEE NIKETAN record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MEDINEE NIKETAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
A1G+831 Dec 2020
B1G+831 Dec 2020
C1G+731 Dec 2020
D1G+731 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2022The Project is a redevelopment project with 4 wings out of which 2 wings were existing members of the society and remaining two wings were for sale. The members have been delive
30 Dec 202231 Dec 2023Due to pending final CC for the building, we were unable to complete the project within the timeline previously permitted by RERA authorities. Now we have received full CC for the

Location, Land & Connectivity

Located at BAMANWADA, MC CHAGLA MARG, Borivali, Mumbai Suburban, 400099. Per the filed land record, the plot is bounded to the north by CTS 57-1, to the south by AIRPORT AUTHORITY PROPERTY, to the east by CTS 58 and to the west by AIRPORT AUTHORITY PROPERTY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Andheri MIDC / SEEPZ3 km
Bandra Kurla Complex (BKC)4 km
Powai / Hiranandani business park5 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Ashtha Pushp Andheri East
possession by Dec 2026 · Indo Build Enterprise
Green Shadow Chsl
possession by Dec 2026 · Green Globe Realty
Swapna Sudha CHS LTD
possession by Dec 2026 · M/S AMO Group
Vishwas Niketan By Viiaan
possession by Dec 2026 · Somani Buildtech LLP
DEM Panache
possession by Jan 2027 · DEM Homes LLP
Rakshi-Elanza
possession by Mar 2027 · OM SAI Builders & Developers

Other RERA-registered projects in Mumbai Suburban

Mediterranean
possession by Mar 2027 · Fortune Investments
Meena House
possession by Mar 2027 · Ramesh R Parekh HUF
Meera Kunj
possession by Dec 2026 · Arham Realty
Meera Upvan CO-Operative Housing Society Limited
possession by Dec 2027 · Yogiraj Builders AND Developers
Meeti Coral
declared completion Dec 2021 · M/S Meeti Developers PVT LTD
Megh Mahal Chsl
possession by Dec 2027 · Samarpan Homes & Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026