MahaRERA Property Intelligence · Thane

METRO HIGHLAND PHASE I

P51700005374 · promoter Metro Developers

Certificate SignedDue 30 Jun 2019

Delivery & Registration

MahaRERA registrationP51700005374
Registered on11 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Metro Developers is the promoter of record on 74 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
R41G+830 Jun 2018
R51G+730 Jun 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The Court Of Civil Judge S D Kalyan144/20132013Matter Is Subjudice
The Court Of Civil Judge S D Kalyan244/20132013Matter Is Subjudice
The Court Of Civil Judge S D Kalyan44/20182018Court Has Ordered Status Quo On Project Land Till Next Hearing Date

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 201930 Jun 2019We, M/s Metro Developers have obtained registration for our project Metro Highland – Phase I, from MAHARERA on August 11, 2017 as an ongoing project. The proposed date of completio

Location, Land & Connectivity

Located at Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by S NO 131, to the south by 18 METER ROAD, to the east by S NO 128 H NO 1 PT and to the west by 12 METER ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park34 km
Andheri MIDC / SEEPZ38 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Metro Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Metro Developers

Metro Developers
Not filing quarterly progress reportsThane

Other RERA-registered projects in Ambernath

24 High Bizbay
possession by Jul 2026 · Apex Infra
Shree Gajanan Enterprises Rukhmini CHS
possession by Jul 2026 · Shree Gajanan Enterprises Rukhmini CHS
Walekar Homes
possession by Aug 2026 · Walekar & Son's Developers
Patels Eirene
possession by Aug 2026 · Pramukh Developers
Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters

Major developers building in Ambernath

Other RERA-registered projects in Thane

Metro Highland - Phase II
declared completion Jun 2026 · Metro Developers
Metro Hive D-1
possession by Dec 2026 · Vihang Infrastructure PVT LTD
Metro Imperial
declared completion Jun 2021 · Metro Balaji Developers
Metro Imperial
possession by Dec 2028 · Pragati Combines
Metro Luxuria
possession by Dec 2027 · Nivara Engineers
Metro Majestic
declared completion Nov 2024 · Nakshatra Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026