MOHINI TOWER

Khar West · MOHINI SHELTORS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006731

Delivery and registration

When is the project declared for completion?

MOHINI TOWER is registered with MahaRERA as P51800006731 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006731
Registered on16 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MOHINI TOWER record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mohini Sheltors is the promoter of record on 9 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MOHINI TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
MOHINI TOWER1G+18-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for MOHINI TOWER, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002306929/01/2018GHANSHYAMDAS MANGARAM SHAHANI AND DR JAYSHRI LAXMANRAO PATIL vs MR. PRAKASH GULABRAI CHAWALAorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court28732010Preadmission

Location, Land & Connectivity

Located at Khar West, Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by EXISTING BUILDING, to the south by EXISTING BUILDING, to the east by EXISTING BUILDING and to the west by ROAD 12 20 MTR. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Lower Parel / Worli business district8 km
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mohini Sheltors Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Mohini Sheltors Private Limited

Mohini Sheltors Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Khar West

Trishaan
possession by Sep 2026 · Raja Builder
Yogi Sea
possession by Sep 2026 · Yogi Limited
Searock Residences
possession by Oct 2026 · Searock Constructions LLP
259 Park Crest
possession by Dec 2026 · Shree Krishna Homes PVT LTD
33 West
possession by Dec 2026 · Silver Lifespaces Private Limited
Benchmark Plaza
possession by Dec 2026 · Benchmark Projects PVT LTD

Major developers building in Khar West

Other RERA-registered projects in Mumbai Suburban

Mohite Marvel
possession by Sep 2026 · Mohite Realtors LLP
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited
Monarch Majestic
possession by Nov 2028 · NEW Monarch Builders AND Contractors
Monarch Prathmesh Chsl
possession by Mar 2028 · Monarch Construction
Monarch Rosewood
declared completion Apr 2025 · Monarch Lifespace LLP
Monarch Trinity
declared completion Apr 2025 · Monarch Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026