Mumbai/Project record

MahaRERA · the public record

MORIVALI AMBERNATH BRONDESBURY CO-OP HSG. SOCIETY LIMITED.

AMBERNATH · MORIVALI AMBERNATH BRONDESBUSRY CO-OP HSG.SOCIETYLIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700019332

Delivery and registration

When is the project declared for completion?

MORIVALI AMBERNATH BRONDESBURY CO-OP HSG. SOCIETY LIMITED. is registered with MahaRERA as P51700019332 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700019332
Registered on23 Jan 2019
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MORIVALI AMBERNATH BRONDESBURY CO-OP HSG. SOCIETY LIMITED. record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MORIVALI AMBERNATH BRONDESBURY CO-OP HSG. SOCIETY LIMITED. in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
MORIVALI AMBERNATH BRONDESBURY CO-OP HSG SOCIETY LIMITED1G+831 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at AMBERNATH, AMBERNATH, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by D P ROAD, to the east by PLOT NO H 8 and to the west by PLOT NO H 6. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Morivali Ambernath Wembley Park CHS LTD
possession by Nov 2028 · Shree Khodiyar Buildcon
Morya Aarambh
declared completion Dec 2023 · Morya Developers
Morya Enclave
possession by Jul 2029 · Not Available
Morya Garden
possession by Apr 2027 · Sumit Developers
Morya Heights
possession by Dec 2027 · Morya Infraconstruct Private Limited
Morya Heights
declared completion Jun 2026 · Morya Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 21 Sep 2026