Mumbai/Project record

MahaRERA · the public record

MUKTA APRATMENT

Thane · SHREE EKVEERA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700011545

Delivery and registration

When is the project declared for completion?

MUKTA APRATMENT is registered with MahaRERA as P51700011545 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700011545
Registered on31 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MUKTA APRATMENT record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shree Ekveera Developers is the promoter of record on 18 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MUKTA APRATMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
A WING1G+8-
B WING1G+8-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for MUKTA APRATMENT, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250023423/01/2025PRADIP VAMANRAO DESHPANDE vs SHREE EKVEERA DEVELOPERSorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Thane Court387/172017Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020DUE TO MORE TIME CONSUME BY TMC TO APPROVAL OF SANCTION PLAN, PLAN WAS SANCTIONED ON 13/10/2017. CURRENT STATUS OF CONSTRUCTION- 95% WORK COMPLETED, PROCEED FOR O.C. AND APPLIED

Location, Land & Connectivity

Located at Thane, Thane, 400601. Per the filed land record, the plot is bounded to the north by H NO 10 16, to the south by H NO 10, to the east by BORDER OF MAJIWADA and to the west by H NO 10. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park12 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Thane

Avesa
possession by Oct 2026 · Jagdale Infrastructure Pvt. Ltd.
Ramashankar CHS LTD
possession by Oct 2026 · SAI Prasad Builders AND Developers
Bhavana Apartment CHS
possession by Nov 2026 · Shree Infra
Sheth Zuri
possession by Dec 2026 · Sheth Developers Private Limited
Musica Apartment
possession by Dec 2026 · E I Construction
Rustomjee LA Familia - Wing A
possession by Dec 2026 · Kapstone Constructions Private Limited

Major developers building in Thane

Other RERA-registered projects in Thane

Mukta Gharonda
declared completion Dec 2025 · Skylark Infrastructures
Mukta Lake City
declared completion Jun 2022 · Kanak Realtors
Mukta Luxuria
declared completion Jan 2024 · Mukta Reality
Mukta Residency Phase 2
declared completion Dec 2023 · Mukta Developers
Mukundam
declared completion Aug 2026 · Shree Ramjeevdani Realtors
Multani Residency
possession by Nov 2026 · M R Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026