Mumbai/Project record

MahaRERA · the public record

Mukta Residency Phase 2

Khidkali · MUKTA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700005154

Delivery and registration

When is the project declared for completion?

Mukta Residency Phase 2 is registered with MahaRERA as P51700005154 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700005154
Registered on10 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Mukta Residency Phase 2 record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mukta Developers is the promoter of record on 23 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

23projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Mukta Residency Phase 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
B-1 ZINIA1G+2531 Dec 2022
B-2 FRESSIA1G+2531 Dec 2022
C-1 POLICE STATION1G+731 Dec 2022
C-2 MUKTA HOUSE1G+631 Dec 2022
A1 Bunglow1G+230 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Khidkali, Kalyan Shill Road, Thane, Thane, 421204. Per the filed land record, the plot is bounded to the north by 19 09 13 73 03 41, to the south by 19 09 13 73 03 41, to the east by 19 09 13 73 03 41 and to the west by 19 09 13 73 03 41. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park17 km
Andheri MIDC / SEEPZ20 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district30 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mukta Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Dombivali

Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons
Neelkamal Residency AND Business Park
possession by Dec 2026 · Neelkamal Buildco
Paramount
possession by Dec 2026 · Metro Dream Homes
Auroville Wing C AND D
possession by Dec 2026 · Arya Construction

Major developers building in Dombivali

Other RERA-registered projects in Thane

Mukundam
declared completion Aug 2026 · Shree Ramjeevdani Realtors
Multani Residency
possession by Nov 2026 · M R Developers
Mumbra Landmark
declared completion Dec 2024 · Jyoti Industries
Munisuvrat Textile Park
possession by Mar 2027 · Munisuvrat Commercial Parks LLP
Musica Apartment
possession by Dec 2026 · E I Construction
Mustafa Empire
possession by Dec 2028 · Mehraj Construction & Co.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026