Mumbai/Project record

MahaRERA · the public record

Runwal Gardens Phase 5 Bldg No. 39 to 42

Dombivali · Runwal Residency Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700031609

Delivery and registration

When is the project declared for completion?

Runwal Gardens Phase 5 Bldg No. 39 to 42 is registered with MahaRERA as P51700031609 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700031609
Registered on03 Nov 2021
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Runwal Gardens Phase 5 Bldg No. 39 to 42 record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Runwal Residency is the promoter of record on 149 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

149projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Runwal Gardens Phase 5 Bldg No. 39 to 42 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29.

BuildingWingsFloorsDeclared completion
Bldg No 391G+29-
Bldg No 401G+29-
Bldg No 411G+29-
Bldg No 421G+29-

Legal and disputes

What disputes are disclosed?

11 complaints are on the MahaRERA record for Runwal Gardens Phase 5 Bldg No. 39 to 42, with orders passed in 7 of them.

11complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000040844023/12/2023Mithilesh Avinash Nakade vs Runwal Gardensorder passed
CC00600000042931518/02/2024Arpita Amit Pendse vs Nancy Salveorder passed
CC00600000054074111/06/2024Ajay Pranjivan Bhuttaiya vs Runwal Residency Pvt Ltdpending / no order on file
CC1250388205/11/2025Runwal Residency Private Limited vs Mrs Sarika Dattaram Palkarorder passed
CC1250388906/11/2025Runwal Residency Private Limited vs Shirish Sopan Patneorder passed
CC1250459923/12/2025Glenn Motes Dsouza vs Runwal Residency Private Limitedpending / no order on file
CC1260000501/01/2026Anil Yadav vs Runwal Residency Private Limitedorder passed
CC1260010707/01/2026Vaijnath Mahadevrao Shinde vs Runwal Residency Private Limitedorder passed
CC1260011608/01/2026Vatsala Vasant Sanap vs Runwal Residency Private Limitedorder passed
CC1260358510/06/2026Vikas Pawar vs Runwal Residency Private Limitedpending / no order on file
CC1260404529/06/2026Manali Manish Jain vs Runwal Residency Private Limitedpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2028a. The said Project was registered in August 2021 i.e. during the COVID-19 pandemic, the after-effects of pandemic created manpower, supply chain related problems, health and safet

Location, Land & Connectivity

Located at Dombivali, Village Gharivali Usarghar Sagaon, Mumbai City, Mumbai City, 421204. Per the filed land record, the plot is bounded to the north by 24 Mtr D P Road, to the south by S No 37 and S No 4-8 pt, to the east by 24 mtr D P Road and to the west by Neighbouring Plot hissa no 4 and hissa no 8. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Runwal Residency Private Limited is the promoter on 18 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Runwal Residency Private Limited project & its RERA track record →

Other flagged projects by Runwal Residency Private Limited

Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane

Other RERA-registered projects in Dombivali

Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons
Neelkamal Residency AND Business Park
possession by Dec 2026 · Neelkamal Buildco
Paramount
possession by Dec 2026 · Metro Dream Homes
Auroville Wing C AND D
possession by Dec 2026 · Arya Construction

Major developers building in Dombivali

Other RERA-registered projects in Thane

Runwal Gardens Phase 6A Bldg No. 53-54
possession by Jun 2029 · Runwal Residency Private Limited
Runwal Gardens Phase 8 Bldg No. 43 And 45
possession by Dec 2026 · Runwal Residency Private Limited
Runwal Gardens - Phase 8 - Bldg No. 44
possession by Mar 2027 · Runwal Residency Private Limited
Runwal Gardens Phase I
declared completion Jun 2025 · Runwal Residency Private Limited
Runwal Lands END
possession by Jun 2029 · Runwal Construction Private Limited
Runwal Lands END - Breeze
possession by Apr 2031 · Runwal Construction Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026