MahaRERA Property Intelligence · Thane

Primrose MHADA 2

P51700053843 · Dombivali · promoter Runwal Residency Private

Certificate SignedDue 31 Mar 2025

Delivery & Registration

MahaRERA registrationP51700053843
Registered on01 Dec 2023
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Runwal Residency Private is the promoter of record on 142 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Primrose MHADA 2 EWS LIG - Building no - 21G+23-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250357307/10/2025Mandar Manohar Manjrekar vs Runwal Residency Private Limitedorder passed

Location, Land & Connectivity

Located at Dombivali, Kalyan Shilphata Road, Mumbai City, Mumbai City, 421204. Per the filed land record, the plot is bounded to the north by Survey no 50 pt, to the south by Survey no 50 pt, to the east by Bldg EWS LIG 1 and to the west by 30 m w D P Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Runwal Residency Private Limited is the promoter on 18 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Runwal Residency Private Limited project & its RERA track record →

Other flagged projects by Runwal Residency Private Limited

Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane
Runwal Residency Private Limited
FlaggedThane

Other RERA-registered projects in Dombivali

Balaji Estate
possession by Jul 2026 · M/s. Sai Balaji Buildcon
Jayram Heights
possession by Jul 2026 · Ashapura Enterprises
Pearl B
possession by Jul 2026 · Lodha Developers Limited
Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons

Major developers building in Dombivali

Other RERA-registered projects in Thane

Primus Business Park
declared completion Oct 2022 · Hemant Kashikar
Primus Homes
possession by Oct 2028 · K K Nirman & Infrastructure LLP
Prince Avenue
declared completion Jun 2026 · Shakti Developers
Prince Tower
possession by Dec 2029 · Prince India Developers
Princess Paradise
declared completion Sep 2024 · Laxminarayan Builders
Prism Industrial Estate
declared completion Oct 2025 · Splendor Shelters PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026