MahaRERA Property Intelligence · Mumbai Suburban

NARAYAN DHAN

P51800015592 · KHAR GYMKHANA · promoter Raaju Naraindas Amarnaani

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800015592
Registered on08 Mar 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
NARAYAN DHAN1G+1731 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KHAR GYMKHANA, 15TH ROAD, Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by SAVITRI SADAN, to the south by 13TH ROAD, to the east by 15TH ROAD and to the west by MORU MILAN BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport4 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district8 km
Powai / Hiranandani business park9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khar West

Trishaan
possession by Sep 2026 · Raja Builder
Yogi Sea
possession by Sep 2026 · Yogi Limited
Searock Residences
possession by Oct 2026 · Searock Constructions LLP
259 Park Crest
possession by Dec 2026 · Shree Krishna Homes PVT LTD
33 West
possession by Dec 2026 · Silver Lifespaces Private Limited
Benchmark Plaza
possession by Dec 2026 · Benchmark Projects PVT LTD

Major developers building in Khar West

Other RERA-registered projects in Mumbai Suburban

Narayan Residency
possession by Jan 2030 · Narayan Vventures
Narmada Plaza
possession by Dec 2029 · M/S Nexzone Fiscal Services PVT LTD
Narulla
possession by Jun 2028 · Majestic Royale Developers
Nasam Chambers
possession by Mar 2029 · Nasam Homes
Nasar Apartment Composite Building B Wing
declared completion Dec 2021 · M/s. Nasar Associates
Nasar Enclave Sale Building A And B Wing
declared completion Jun 2026 · M/s. Nasar Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026