MahaRERA · the public record
NARMADA VIHAR
Thane · K.M.DEVELOPERS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2024
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P99000006696
Delivery and registration
When is the project declared for completion?
NARMADA VIHAR is registered with MahaRERA as P99000006696 and the promoter has declared completion for 30 Jun 2024.
30 Jun 2024
declared completion
27months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P99000006696 |
| Registered on | 16 Aug 2017 |
| Promoter-declared completion | 30 Jun 2024 |
| Current status | Certificate Signed |
| Against today | about 27 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NARMADA VIHAR record 28 quarterly progress reports since registration.
28quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for NARMADA VIHAR in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| BUILDING NO 1 | 1 | G+4 | 31 Aug 2019 |
| BUILDING NO 2 | 1 | G+4 | 31 Jul 2019 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Aug 2020 | WE NEED TO MODIFY OUR PROJECT DETAILS AS WE HAD MENTIONED 2 BLDG IN A SINGLE PROJECT WE NEED TO CHANGE BOTH THE BUILDINGS AS SEPARATE PROJECT AND SEPARATE DATE OF COMPLETION. AT PR |
| 30 Aug 2020 | 31 Dec 2023 | We had started project and done the plinth work till date, but due to no sale of flats and shops we are slowly doing construction work, so there is delay in construction. Also as t |
Location, Land & Connectivity
Located at Thane, Thane, 401504. Per the filed land record, the plot is bounded to the north by BUILDING NO 3, to the south by BOISAR KURGAON ROAD, to the east by BOUNDARY WALL and to the west by INTERNAL LAYOUT ROAD. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~80 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 80 km |
| Powai / Hiranandani business park | 82 km |
| Chhatrapati Shivaji Int'l Airport | 84 km |
| Bandra Kurla Complex (BKC) | 87 km |
| Lower Parel / Worli business district | 93 km |
| Nariman Point / Fort | 101 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.