Mumbai/Project record

MahaRERA · the public record

NARMADA VIHAR

Thane · K.M.DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000006696

Delivery and registration

When is the project declared for completion?

NARMADA VIHAR is registered with MahaRERA as P99000006696 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000006696
Registered on16 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NARMADA VIHAR record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NARMADA VIHAR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NO 11G+431 Aug 2019
BUILDING NO 21G+431 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Aug 2020WE NEED TO MODIFY OUR PROJECT DETAILS AS WE HAD MENTIONED 2 BLDG IN A SINGLE PROJECT WE NEED TO CHANGE BOTH THE BUILDINGS AS SEPARATE PROJECT AND SEPARATE DATE OF COMPLETION. AT PR
30 Aug 202031 Dec 2023We had started project and done the plinth work till date, but due to no sale of flats and shops we are slowly doing construction work, so there is delay in construction. Also as t

Location, Land & Connectivity

Located at Thane, Thane, 401504. Per the filed land record, the plot is bounded to the north by BUILDING NO 3, to the south by BOISAR KURGAON ROAD, to the east by BOUNDARY WALL and to the west by INTERNAL LAYOUT ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~80 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ80 km
Powai / Hiranandani business park82 km
Chhatrapati Shivaji Int'l Airport84 km
Bandra Kurla Complex (BKC)87 km
Lower Parel / Worli business district93 km
Nariman Point / Fort101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K.m.developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by K.m.developers

Other RERA-registered projects in Pasthal

Mahavir Business Centre
possession by Dec 2026 · Rajesh Developers
Balaji Complex Phase-2
possession by Dec 2027 · B R Housing
Mahavir Neytra
possession by Dec 2027 · Rajesh Construction
Mahavir Vihar Building NO 4 Type E
possession by Dec 2027 · Rajesh Construction
Shree Samarth Apartment
Not filing quarterly progress reports · possession by Dec 2027 · Aakash Keshmani Singh
Ramsetu
possession by Aug 2029 · Satvik Builders & Developers

Other RERA-registered projects in Palghar

Natraj
possession by Dec 2028 · Canopy Infra
Naval Baug Building No 1 And 2B
declared completion Mar 2022 · Ahura Mazda Developers
Navkar City
declared completion Dec 2021 · Navkar Developers
Navkar City Phase I Part 14
possession by Dec 2028 · Navkar Developers
Navkar City Phase I Part 2
possession by Dec 2026 · Navkar Estate And Homes Pvt Ltd
Navkar City Phase-I-Part-4
possession by Dec 2026 · Navkar Estate & Home Pvt Lts

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026