NATWAR HOUSE CO-OP HSG SOC LTD

Mumbai Suburban · PADAMAVATI BUILDERS AND INFRASTRUCTURES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700010895

Delivery and registration

When is the project declared for completion?

NATWAR HOUSE CO-OP HSG SOC LTD is registered with MahaRERA as P51700010895 and the promoter has declared completion for 31 Mar 2024.

31 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700010895
Registered on31 Aug 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NATWAR HOUSE CO-OP HSG SOC LTD record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Padamavati Builders is the promoter of record on 3 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NATWAR HOUSE CO-OP HSG SOC LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
NATWAR HOUSE CHSL1G+1031 Dec 2019

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for NATWAR HOUSE CO-OP HSG SOC LTD, with orders passed in 4 of them.

7complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250153008/05/2025NATWAR HOUSE CO OPERATIVE HSG SOCIETY vs PADAMAVATI BUILDERS AND INFRASTRUCTURESorder passed
CC1250440010/12/2025GOVINDSARAN B AGARWAL vs PADAMAVATI BUILDERS AND INFRASTRUCTURESorder passed
CC1250440110/12/2025CHESTA MANISH AGARWAL vs PADAMAVATI BUILDERS AND INFRASTRUCTURESorder passed
CC1250448716/12/2025KRISHNA KUMAR CHATURVEDI vs PADAMAVATI BUILDERS AND INFRASTRUCTURESorder passed
CC1260236522/04/2026Rahul Kantaprasad Chaurasia vs PADAMAVATI BUILDERS AND INFRASTRUCTURESpending / no order on file
CC1260280314/05/2026VIJAYA PRAKASH MISAL vs PADAMAVATI BUILDERS AND INFRASTRUCTURESpending / no order on file
CC1260293619/05/2026SUDHAKAR NAGANNA SHETTY vs PADAMAVATI BUILDERS AND INFRASTRUCTURESpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2020BALANCE FSI TO BE LOADED
31 Dec 202031 Dec 2022ROAD FSI AND NEW ANCILLARY FSI IS TO BE LOADED AND PLANS IS TO BE SUBMITTED IN DUE COURSE, COVID-19 PANDEMIC HAS CREATED A LOT OF TROUBLE IN OUR REAL ESTATE SECTOR LEADING TO SHORT
31 Dec 202231 Mar 2024NEW FSI AS PER NEW UDCPR-2020 , WE HAVE SUBMITTED PLANS IN MIRA-BHYANDAR MUNICIPAL CORPORATION FOR FURTHER CC WITH ALL CONCENTS OF EXISTING MEMBERS AND NEW FLAT/SHOP ALLOTEES , WE

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 401105. Per the filed land record, the plot is bounded to the north by POOJA BLDG, to the south by ROAD, to the east by ROAD and to the west by KALPITA BLDG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ17 km
Powai / Hiranandani business park19 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander East

Gayatri Elegance
possession by Dec 2026 · Gayatrikripa Developers Private Limited
Basera Heights
possession by Dec 2026 · Kamruddin Hasmullah Siddique
Durga Enclave
possession by Dec 2026 · Anmol Developers
Ranuja Ramdev C Type
possession by Dec 2026 · Ranuja Ramdev C Type
Surya Heritage A
possession by Dec 2026 · Arun Construction CO
The Pentagon
possession by Dec 2026 · Anjani Kumar Realty Private Limited

Other RERA-registered projects in Thane

NAV Anuradha Darshan CHS LTD
declared completion Dec 2024 · Ameya Enterprises
NAV Ashokvan Cooperative Housing Society LTD
possession by Apr 2027 · Gagan Developers AND Engineers
NAV Avani CHS
declared completion Jan 2025 · Mangalya Infra
NAV Balaji CO-OP Hsg. Soc. LTD
declared completion Jun 2026 · Ruturaj Developers
Nav Omkar
possession by Dec 2028 · Avighna Redevelopers Nav Omkar
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.