Mumbai/Project record

MahaRERA · the public record

NEELKANTH PALACE

BADLAPUR · PUSHPLATA SUBHASH GHULE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700034676

Delivery and registration

When is the project declared for completion?

NEELKANTH PALACE is registered with MahaRERA as P51700034676 and the promoter has declared completion for 31 Mar 2025.

31 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700034676
Registered on20 Apr 2022
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEELKANTH PALACE record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEELKANTH PALACE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
NEELKANTH PALACE1G+631 Mar 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BADLAPUR, BADLAPUR, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by S NO 184, to the south by 18 M W D P ROAD, to the east by 18 M W D P BORADPADA and to the west by S NO 272. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Jagannath Paradise
possession by Sep 2026 · Mayur Group
JAY Meghdoot Chsl
possession by Sep 2026 · S R Developers
Kendale Emeralds
possession by Sep 2026 · Kendale Developers
Krishna Sudama Residency
possession by Sep 2026 · SAI Homes
MAA Bhawani Empire
Deregistered by MahaRERA · possession by Sep 2026 · MAA Bhawani Construction
Raghu Anand Villa
possession by Sep 2026 · United Developers

Other RERA-registered projects in Thane

Neelkanth Palm Avenue
possession by Dec 2029 · Neelkanth Infratech
Neelkanth Palm President
possession by Dec 2029 · Neelkanth Infratech
Neelkanth Palms
possession by Dec 2028 · Neelkanth Developers
Neelkanth Royale Palms - F Wing Phase II
possession by Dec 2026 · Neelkanth Associates
Neelkanth Sadan
declared completion Jul 2026 · Shreeji Enterprises
Neelkanth Woods Bungalow L 57
declared completion Nov 2021 · T Bhimjyani Realty Pvt.ltd.

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026