Neev Amberwood

Mumbai City · Neev Infrastructure Pvt Ltd

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002969

Delivery and registration

When is the project declared for completion?

Neev Amberwood is registered with MahaRERA as P51800002969 and the promoter has declared completion for 31 Mar 2019.

31 Mar 2019

declared completion

90months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002969
Registered on04 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 90 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Neev Amberwood record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Neev Infrastructure is the promoter of record on 21 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

21projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Neev Amberwood in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Neev Amberwood - A Wing1G+16-
Neev Amberwood - B Wing1G+15-
Neev Amberwood - C Wing1G+16-
Neev Amberwood - D Wing1G+17-

Legal and disputes

What disputes are disclosed?

9 complaints are on the MahaRERA record for Neev Amberwood, with orders passed in 9 of them.

9complaints

9with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005740924/12/2018Neev Amberwood New Flat Owners Association vs Navnit Co-operative Housing Society Ltdorder passed
CC00600000007916906/05/2019Mr. Sushil M Jain & Nitasha S Jain vs Neev Infrastructure Private Limitedorder passed
CC00600000014099715/10/2019SURFACE INFRASTRUCTURE PRIVATE LIMITED vs Neev Amberwood New Flat Owner Associationorder passed
CC00600000017175503/12/2019Hitesh Mafatlal Shah vs Neev Infrastructure Private Limitedorder passed
CC00600000005642225/10/2018Neev Amberwood New Flat Owners Association & others as per Annexure A vs Neev Infrastructure Private Limitedorder passed
CC00600000007867028/03/2019Sharwan Kumar Agarwal vs Neev InfrastructurePvt.Ltdorder passed
CC00600000007868829/03/2019AJAY B SHAH vs Neev InfrastructurePvt.Ltd.order passed
CC00600000007870329/03/2019AJAY B SHAH vs Neev Infrastructure Pvt.Ltdorder passed
CC00600000007870429/03/2019Ajay B Shah vs Neev Infrastructure P Ltd.order passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court11332013On Going
High Court3632019Pre Admission
Maha ReraNew Buyers,Navnit Society and Developer2019On Going

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400058. Per the filed land record, the plot is bounded to the north by Survey No 67-B, to the south by Survey No 84B Survey No 84 Hissa No 4 , to the east by Survey No 81 Hissa No 3 Survey No 84 Hissa No 4 and to the west by Survey No 85 Hissa No 2 Survey Nos 84B and 84A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park7 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya
La Alteza
possession by Dec 2026 · Emerald Developers

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Neev Galaxy
declared completion Sep 2025 · Neev Infrastructure Pvt. Ltd.
Neha Apartments
declared completion Jun 2023 · Yashraj Corporation
Nehru Nagar Guruprasad CO-Operative Housing Society Limited
declared completion Dec 2025 · Deraiya Realtors Private Limited
Nehru Nagar Madhukunj Co-Operative Housing Society Limited
declared completion Mar 2024 · Mishal Construction Private Limited
Nehru Nagar Nirmal C.h.s. Ltd
possession by Dec 2026 · Deraiya Realtors Private Limited
Nehru Nagar Panchratna CHS Ltd, Bldg. No.5
declared completion Dec 2025 · Parsn Construction AND Developers Privat

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026