MahaRERA Property Intelligence · Raigarh

NEXUS HEIGHTS

P52000013983 · promoter Nexus Realty

Certificate SignedDue 31 Dec 2017

Delivery & Registration

MahaRERA registrationP52000013983
Registered on07 Nov 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 103 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nexus Realty is the promoter of record on 39 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
NEXUS HEIGHTS1G+18-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Panvel, Raigarh, 410208. Per the filed land record, the plot is bounded to the north by 15 METER WIDE ROAD, to the south by PLOT NO-9, to the east by 15 METER WIDE ROAD and to the west by PLOT NO-11. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park21 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport24 km
Andheri MIDC / SEEPZ25 km
Lower Parel / Worli business district29 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
3anaika
possession by Dec 2026 · Arihant Enterprises

Major developers building in Taloja

Other RERA-registered projects in Raigarh

Nexus Peace
possession by Dec 2026 · Nexus Infra
Nexus View
declared completion Dec 2023 · Nexus Infra
Niharika Absolute
declared completion Jan 2026 · Juhi Infrabuild LLP
Niharika Mirage
declared completion Dec 2021 · Juhi Habitat Pvt. Ltd.
Nikhil Park
possession by Dec 2026 · Gurudev Developers
Nikhil Residency
declared completion Dec 2019 · Kasturi Builders & Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026