MahaRERA · the public record
Nirvana Bougainvilla
Usale · Kishor Otarmal Jain
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000050750
Delivery and registration
When is the project declared for completion?
Nirvana Bougainvilla is registered with MahaRERA as P52000050750 and the promoter has declared completion for 31 Dec 2027.
31 Dec 2027
declared completion
15months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000050750 |
| Registered on | 28 Apr 2023 |
| Promoter-declared completion | 31 Dec 2027 |
| Current status | Certificate Signed |
| Against today | 15 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Nirvana Bougainvilla record 16 quarterly progress reports since registration.
16quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Construction
How much construction cost has been reported?
In Nirvana Bougainvilla, ₹7.98 Cr of a declared ₹9.14 Cr estimated project cost is reported as incurred, about 87.4%, as at the last certified filing with MahaRERA.
87.4%
₹7.98 Cr
of ₹9.14 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Nirvana Bougainvilla, 35 of 49 plots filed with MahaRERA are recorded as sold or booked, about 71%, and 14 remain available.
71%sold
35 of 49 plots
Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What the filings record, plot by plot
Read from MahaRERA on 19 September 2026
MahaRERA publishes, plot by plot, what this promoter filed: which plots are sold and which are not, the filed area of each, and for the sold ones the registered agreement value — the consideration filed for that specific plot. On this project 35 plots carry one, and 14 of the 49 are recorded unsold.
Here is one of those unsold plots, priced against what buyers of comparable plots on the same filing actually filed:
| Plot | Area | Filed for comparable plots on the same filing | Based on |
|---|---|---|---|
| 94 | 2,228 sqft | Rs 19.76 lakh typical, over Rs 19.75 lakh to Rs 20.34 lakh | 7 filed on this stack |
A filed consideration is what was registered for one plot. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the plot is available to you today. Only one observation of this ledger so far: no change can be reported yet.
In Nirvana Bougainvilla, 11 of the 14 unsold plots have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Legal and disputes
What disputes are disclosed?
1 complaint is on the MahaRERA record for Nirvana Bougainvilla, with orders passed in 0 of them.
1complaint
0with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12604112 | 01/07/2026 | Shruti Vijaykumar Nanda vs Kishor Otarmal Jain | pending / no order on file |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2027 | The delay was due to a shortage of manpower and insufficient financial resources. |
Location, Land & Connectivity
Located at Usale, Survey No- 21/1, 22/0, 23/0, 25/0, 24/1, 24/4, 26/3, Roha, Raigarh, 410205. Per the filed land record, the plot is bounded to the north by Survey No-24-2 24-3 26-1 26-2, to the south by Survey No-21-2 21-3 24-5A 26-4, to the east by Survey No-2 and 3 and to the west by Boundary Village Chive. These are the boundaries as recorded in the filed land record.