Mumbai/Project record

MahaRERA · the public record

OM HEIGHTS

MALAD · KOSMOS & APPLE REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800003615

Delivery and registration

When is the project declared for completion?

OM HEIGHTS is registered with MahaRERA as P51800003615 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800003615
Registered on06 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OM HEIGHTS record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kosmos Apple Realty is the promoter of record on 10 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OM HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
OM HEIGHTS1G+2430 Jun 2022

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for OM HEIGHTS, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000030339623/11/2022Mukesh Sevantilal Shah vs Kosmos & Apple Realtyorder passed
CC00600000039775808/10/2023Hemant Ashok Jagtap vs Mukund Parmar, Partner, Kosmos & Apple Realtyorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022due to current covid situation and lockdown imposed by state government and nonviability of labour at our site.
30 Jun 202230 Jun 2023we are taking rera extension for the reason of OC process with the consent of our parties
30 Jun 202331 Dec 2023we here with request you for requirement for extension for 6 month till 31/12/2023 for complete the OC Compliances and waiting for Occupancy Certificate.

Location, Land & Connectivity

Located at MALAD, HAJI BAPU ROAD, Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by EXISTING DP ROAD, to the south by TOWER 28, to the east by HAJI PABU ROAD and to the west by ARIHANT ASHISH CHSL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport10 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district20 km
Nariman Point / Fort28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad East

Amann Highland Park
possession by Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
possession by Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd
Royal Pristo
possession by Dec 2026 · Royal Realtors
Spring Meadows
possession by Dec 2026 · Renaissance Enterprises

Other RERA-registered projects in Mumbai Suburban

OM Jagdish Chsl-Phase 1
declared completion Jul 2021 · Ssakash Developers & Builders Pvt Lt
Om Kailash Ganga CHS LTD
possession by Oct 2027 · R K Developers
Om Laxmi Sadan CHS Ltd
declared completion Mar 2025 · Maverick Realtors
OM Makarand Heights
possession by Dec 2026 · D D Infra
OM Mayuresh
possession by Dec 2026 · M/s Keytech
OM Nandadeep CO-OP. Hsg. Soc. LTD
possession by Oct 2026 · OM Nandadeep CO-OP Housing Society Limit

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026