29 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005047

Delivery and registration

When is the project declared for completion?

ONE BKC is registered with MahaRERA as P51800005047 and the promoter has declared completion for 29 Dec 2020.

29 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005047
Registered on09 Aug 2017
Promoter-declared completion29 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ONE BKC record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ONE BKC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
ONE BKC B and C Wing Part1G+2230 Jun 2019

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for ONE BKC , with orders passed in 6 of them.

7complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001222207/12/2017HEAVY HYDRAULICS (INDIA) PRIVATE LIMITED vs M/s. Raghuleela Builders Pvt. Ltd.order passed
CC00600000005496016/06/2018Heavy Hydraulics Private Limited vs Raghuleela Builders Private Limitedorder passed
CC00600000002309730/01/2018Impressa Developers Private Limited vs Raghuleela Builders Private Limitedorder passed
CC00600000002342219/02/2018Meyer Organics Private Limited vs Raghuleela Builders Private Limitedorder passed
CC00600000008978218/06/2019Mysore Petro Chemicals Limited vs Raghuleela Builders Pvt. Ltd.order passed
CC00600000019638718/03/2021Creative Propack Limited vs Raghuleela Builders Private Limitedorder passed
CC00600000021016225/02/2022JBandBrothers PvtLtd vs RaghuleelaBuildersPvtLtdpending / no order on file

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. 4 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court5862017Pending
Maha ReraCC0060000000234222018Pending
Bombay High CourtL 2122019Interim Order Recd
Maha ReraCC0060000000230972018Disposed Off
Maha ReraCC0060000000549602019Pending
Bombay High CourtL 7072019Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2020We have applied to the concerned authorities for granting Occupation Certificate and are awaiting receipt of the same.

Location, Land & Connectivity

Located at Bandra East, C Block, Andheri, Mumbai Suburban, 400051. Per the filed land record, the plot is bounded to the north by Abutting plot C-64, to the south by Abutting RG-2, to the east by Abutting MCA club and to the west by A Wing and MMRDA STP. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district8 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bandra East

A And O Estado
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Builders AND Developers
Antariksh Ace
possession by Dec 2026 · Pittie Antariksh Realty Private Limited
Bandra North Gulmohar Avenue
possession by Dec 2026 · Shivalik Ventures Private Limited
Gurukrupa Nirmalam
possession by Dec 2026 · Gurukrupa Realcon Infrastructure LLP
LEO Eminence
possession by Dec 2026 · LEO Infrastructure Private Limited
Mayur Tower
possession by Dec 2026 · Geopreneur Spire Realty

Major developers building in Bandra East

Other RERA-registered projects in Mumbai Suburban

ONE Crystal
declared completion Dec 2025 · Goldnest Spaces LLP
One Garden Avenue
possession by Jul 2030 · DNK Developers LLP
ONE Jogeshwari
possession by Dec 2026 · Unique Developers
ONE Meraki - Wing A & Wing B
declared completion Dec 2025 · Meraki Habitats LLP
One Meraki Wing C And Wing D
possession by Dec 2026 · Meraki Habitats LLP
One Meraki Wing E
possession by Dec 2026 · Meraki Habitats LLP

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.