Mumbai/Project record

MahaRERA · the public record

ONYX RESIDENCY

Mumbai Suburban · ONYXBUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005402

Delivery and registration

When is the project declared for completion?

ONYX RESIDENCY is registered with MahaRERA as P51800005402 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005402
Registered on11 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ONYX RESIDENCY record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ONYX RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
ONYX RESIDENCY1G+15-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ONYX RESIDENCY, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019705923/05/2021Mr Mohammed Saeed Ali Mullaji & Mrs Fawziyah Mohammed Saeed Mullaji vs Onyx Buildersorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020The FSI is increase from 2 to 2.5 and we have to carry out the work for full completion and for that we wants an extension.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400070. Per the filed land record, the plot is bounded to the north by ARAM BAUG CHS LTD, to the south by KAPLESHWAR CHS LTD, to the east by MILAP CHS LTD and to the west by LBS ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport2 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kurla West

Yojan One
possession by Sep 2026 · Meru Realty LLP
Imperial Heights
possession by Nov 2026 · Sumukha Realtors
Buddha Vihar CHS LTD
possession by Dec 2026 · M/S Regal Builders AND Developers
Khaliliya Complex
possession by Dec 2026 · Dani Builders AND Developers
Mantri Business Plaza
possession by Dec 2026 · Mantri Brothers
Rehmaniya Apartments
possession by Dec 2026 · S & S Enterprises

Major developers building in Kurla West

Other RERA-registered projects in Mumbai Suburban

Optima
declared completion Dec 2023 · Unirock Developers
Optimus
possession by Dec 2026 · Panchnaad Developers
Opulence
declared completion Dec 2020 · Sidhivinayak Constructions
Opulence
possession by Dec 2029 · Ariha Buildtech LLP
Opulent
declared completion Feb 2026 · Reki Developers LLP
Oracle
possession by Dec 2029 · Hariom Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026