Mumbai/Project record

MahaRERA · the public record

OPTIMA

Marol Andheri · UNIROCK DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007736

Delivery and registration

When is the project declared for completion?

OPTIMA is registered with MahaRERA as P51800007736 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007736
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OPTIMA record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OPTIMA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
OPTIMA REHAB1G+13-
OPTIMA SALE1G+14-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for OPTIMA, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019463722/10/2020Raees Qureshi vs Unirock Developersorder passed

Location, Land & Connectivity

Located at Marol Andheri, Mittal Ind. Estate Road, Ward E, Mumbai City, 400059. Per the filed land record, the plot is bounded to the north by CTS No 1427 and Mittal Industrial Estate, to the south by CTS No 1427 and Mittal Industrial Estate, to the east by CTS No 1651-B and to the west by CTS No 1427 and Mittal Industrial Estate. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park3 km
Andheri MIDC / SEEPZ3 km
Bandra Kurla Complex (BKC)5 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Royal Green
possession by Dec 2026 · Admire Revive Builder & Developer
VKG Estates
possession by Dec 2026 · Greenery Rock LLP
59 Avenue
possession by Dec 2026 · M/s Ganesh Vishal Infra Engineering Priv
Gateway Residences
possession by Dec 2026 · Infinity Narayani Associates
LA Grace
possession by Dec 2026 · Ecohomes Ventures
Park Royale Phase III
possession by Dec 2026 · Shivranjani Properties LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Optimus
possession by Dec 2026 · Panchnaad Developers
Opulence
declared completion Dec 2020 · Sidhivinayak Constructions
Opulence
possession by Dec 2029 · Ariha Buildtech LLP
Opulent
declared completion Feb 2026 · Reki Developers LLP
Oracle
possession by Dec 2029 · Hariom Realty
Orchid Heights
declared completion Jun 2026 · Nimesh Kirtikumar Shah

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026