OPULENCE

Chembur · SIDHIVINAYAK CONSTRUCTIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002068

Delivery and registration

When is the project declared for completion?

OPULENCE is registered with MahaRERA as P51800002068 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002068
Registered on31 Jul 2017
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OPULENCE record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sidhivinayak Constructions is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OPULENCE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
OPULENCE1G+2331 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2020The New DCPR was introduced on 8th May 2018. It was supposed to be functional from 23rd June, 2018. Now for reason unexplained, they have delayed the implementation date to 1st Sep
30 Jun 202030 Jun 2020We would like to inform you that our completion date of our above project is 31.12.2018. The delay for the project "OPULENCE" is for the reasons which are genuine and stated bel
30 Jun 202030 Jun 2020We would like to inform you that we have taken consent to the proposed modification as required under the provision of the section 7(3) of the Act from majority of the allottees sc

Location, Land & Connectivity

Located at Chembur, Chembur, Kurla, Mumbai Suburban, 400088. Per the filed land record, the plot is bounded to the north by D P ROAD CTS NO 256B, to the south by CTS NO 272B, to the east by CTS NO 256D AND 272A and to the west by CTS NO 268A AND 271. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport8 km
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Lower Parel / Worli business district12 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sidhivinayak Constructions is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Sidhivinayak Constructions

Sidhivinayak Constructions
FlaggedMumbai Suburban
Sidhivinayak Constructions
FlaggedMumbai Suburban

Other RERA-registered projects in Deonar

Surve Tower
possession by Dec 2026 · Meena Vikas Raikar
Gagan Giri Co-Operative Housing Society Limited
Not filing quarterly progress reports · possession by Dec 2026 · Mishal Construction Private Limited
Akshar Amar Mansion
possession by Mar 2027 · Akshar Properties
Anuvidnyan Nagar Co-Op. Housing Society Ltd
possession by Jun 2027 · Makwise Homes LLP
Purva Clermont Wing A
possession by Jun 2027 · Puravankara Limited
Purva Clermont Wing B
possession by Jun 2027 · Puravankara Limited

Major developers building in Deonar

Other RERA-registered projects in Mumbai Suburban

Opulence
possession by Dec 2029 · Ariha Buildtech LLP
Opulent
declared completion Feb 2026 · Reki Developers LLP
Oracle
possession by Dec 2029 · Hariom Realty
Orchid Heights
declared completion Jun 2026 · Nimesh Kirtikumar Shah
Orchid Residency
declared completion Apr 2025 · Bombay Slum Redevelopment Corporation Pv
Orchid Tower
possession by Mar 2027 · Shree Laxmi Estate Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.