MahaRERA Property Intelligence · Thane

ORACLE BUSINESS HUB

P51700019653 · WAGLE ESTATE · promoter Ekta Developers

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP51700019653
Registered on20 Feb 2019
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ekta Developers is the promoter of record on 42 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
ORACLE BUSINESS HUB1G+731 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at WAGLE ESTATE, ROAD NO. 16Z, Thane, Thane, 400604. Per the filed land record, the plot is bounded to the north by PLOT NO A-198, to the south by ROAD NO 16 Z, to the east by ROAD NO 16 and to the west by PLOT A -180. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ekta Developers is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Ekta Developers project & its RERA track record →

Other RERA-registered projects in Wagle Estate

Urban Villa
possession by Jul 2026 · Yash Infra
One Wagle
possession by Oct 2026 · Sagar Nirman Spaces
Bhairaav Milestone Phase II
possession by Dec 2026 · Sharpmind Consultancy Services Private L
Aura Business Center
possession by Dec 2026 · AUM Developers
Centura Square
possession by Dec 2026 · Supper Squarefeet Infraventures LLP
O22 Business Park
possession by Dec 2026 · Midas Touch

Other RERA-registered projects in Thane

Orange Aura
declared completion Dec 2021 · Orange Realtors
Orbit Business HUB
possession by Dec 2028 · Ekatva Developers
Orchid
declared completion Mar 2019 · Mehta Realtors
Orchid
declared completion Jul 2019 · Royale Urbanspace LLP
Orchid A To L
declared completion Jun 2018 · Palava Dwellers Pvt Ltd
Orchid Arcade
possession by Dec 2028 · Swastik Anmol Builders AND Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026