MahaRERA Property Intelligence · Thane

Padamavati Royal Phase 1

P51700023535 · Titwala · promoter Sujeet Kumar Jeetpratap

Certificate SignedDue 28 Nov 2025

Delivery & Registration

MahaRERA registrationP51700023535
Registered on18 Dec 2019
Promoter-declared completion28 Nov 2025
Current statusCertificate Signed
Against todayabout 8 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sujeet Kumar Jeetpratap is the promoter of record on 4 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Building 041G+730 Nov 2024
Building 051G+730 Nov 2024
Building 061G+730 Nov 2024
Building 071G+730 Nov 2024
Building 081G+730 Nov 2024
Building 091G+730 Nov 2024
Building 171G+730 Nov 2024
Building 181G+730 Nov 2024
Building 191G+730 Nov 2024
Building 201G+730 Nov 2024
Shop1G+230 Nov 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Titwala, CTS`81/1, 98/3A, 101/2, 102, 103/1, Thane, Thane, 421605. Per the filed land record, the plot is bounded to the north by 103P 81P, to the south by 98 101 82, to the east by 179 PADA and to the west by 30 mm Wide DP road in SNo 98. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~154 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park154 km
Andheri MIDC / SEEPZ155 km
Chhatrapati Shivaji Int'l Airport159 km
Bandra Kurla Complex (BKC)161 km
Lower Parel / Worli business district169 km
Nariman Point / Fort176 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sujeet Kumar Jeetpratap Singh is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sujeet Kumar Jeetpratap Singh

Sujeet Kumar Jeetpratap Singh
Past its declared completion dateThane
Sujeet Kumar Jeetpratap Singh
FlaggedThane
Sujeet Kumar Jeetpratap Singh
FlaggedThane

Other RERA-registered projects in Titwala

Marathe Tower
possession by Jul 2026 · Saiji Developers
Marathe Elenza
possession by Jul 2026 · Saiji Developers
Ganpati Heights
possession by Sep 2026 · Manoj Prabhakar Patil
Indrayani
possession by Oct 2026 · Naresh Yashwant Patil
Mantra
possession by Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
possession by Nov 2026 · Rustagi Estates Private Limited

Other RERA-registered projects in Thane

Padamavati Royal Phase 2
possession by Dec 2029 · Sujeet Kumar Jeetpratap Singh
Padmadisha Paradise
declared completion Oct 2020 · Padmadisha Paradise
Padmadisha Paradise - Building 2
possession by Dec 2026 · Padmadisha Paradise
Padmadisha Paradise Building Type - 3
possession by Dec 2028 · Padmadisha Paradise
Padmalaxmi
declared completion Mar 2018 · Kedar Bhikaji Bapat
Padmanabh
declared completion Oct 2023 · Yash Govinda Build Infra LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026