Mumbai/Project record

MahaRERA · the public record

Lotus

Near Upper Thana Lodha Project · Sujeet Kumar Jeetpratap Singh

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700014776

Delivery and registration

When is the project declared for completion?

Lotus is registered with MahaRERA as P51700014776 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700014776
Registered on02 Jan 2018
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Lotus record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sujeet Kumar Jeetpratap is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Lotus in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Lotus1G+630 Sep 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Near Upper Thana Lodha Project, Anjur Road, Thane, Thane, 421302. Per the filed land record, the plot is bounded to the north by 205 2P Open Land, to the south by 205 2P Open Land, to the east by Village Road and to the west by 205 2P Open Land. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ21 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district33 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sujeet Kumar Jeetpratap Singh is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sujeet Kumar Jeetpratap Singh

Sujeet Kumar Jeetpratap Singh
FlaggedThane
Sujeet Kumar Jeetpratap Singh
FlaggedThane

Other RERA-registered projects in Bhiwandi

Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited
Anantam Heights
possession by Oct 2026 · Kanak Realty
Upper Thane - Woodlands A, B AND J
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Lotus
declared completion Dec 2025 · Padma Developers
Lotus CHS
possession by Apr 2028 · Bhandari Realty
Lotus Pride
possession by Dec 2027 · Pankaj Pandharinath Jage
Lotus Residency
possession by Mar 2027 · Kulvinder Infrastructure Private Limited
Lumos 1
possession by Dec 2031 · Reva Realty Developers LLP
Lumos Crest
possession by Dec 2031 · Reva Realty Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026