Mumbai/Project record

MahaRERA · the public record

PANNA CASTLE APARTMENT

VIRAR EAST · SHERAJ SHAIKH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000049084

Delivery and registration

When is the project declared for completion?

PANNA CASTLE APARTMENT is registered with MahaRERA as P99000049084 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000049084
Registered on30 Jan 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PANNA CASTLE APARTMENT record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PANNA CASTLE APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
PANNA CASTLE APARTMENT1G+831 Dec 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VIRAR EAST, VIRAR, Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by RADHANGAR BUILDING, to the south by VARDA MAHALAXMI APT, to the east by KAMAT PARK and to the west by VIDYAMANDIR SCHOOL. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar East

Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Jivdani Mauli
Not filing quarterly progress reports · possession by Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon
Radheya Enterprises
possession by Dec 2026 · Divesh Ratilal Shah
SAI Baba Nagar
possession by Dec 2026 · VED Ganga

Other RERA-registered projects in Palghar

Pantan Synergy
declared completion Dec 2025 · Pantan Infraa Private Limited
Paradise
declared completion Dec 2021 · Divekar Construction
Paradise Avenue
possession by Dec 2026 · SAI Paradise Developers
Paradise B Wing
declared completion Dec 2023 · Divekar Construction
Paramount Enclave Bldg NO 4
declared completion Mar 2026 · AV Affordable Housing LLP
Paramount Enclave Bldg NO 5B
declared completion Mar 2024 · Admire Sarvada Builder & Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026