Mumbai/Project record

MahaRERA · the public record

PARASNATH NAGRI

UMROLI · MATAJI DEVELOPER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000023164

Delivery and registration

When is the project declared for completion?

PARASNATH NAGRI is registered with MahaRERA as P99000023164 and the promoter has declared completion for 01 Sep 2023.

01 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000023164
Registered on05 Dec 2019
Promoter-declared completion01 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARASNATH NAGRI record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mataji Developer is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARASNATH NAGRI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NO-5, TYPE G, WING B1G+401 Sep 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at UMROLI, UMROLI, Vasai, Palghar, 401209. Per the filed land record, the plot is bounded to the north by AS PER LAYOUT 154A, to the south by AS PER LAYOUT 154A, to the east by AS PER LAYOUT 154A and to the west by AS PER LAYOUT 154A. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara East

Model Cooperative Housing Society LTD
possession by Oct 2026 · Sai Vaishnav Infra Llp
N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
possession by Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
possession by Dec 2026 · MAA Guru Construction
Imperialparamount
possession by Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
possession by Dec 2026 · Blue OAK Infrastructure

Other RERA-registered projects in Palghar

Parasnath Township
possession by Mar 2028 · Shreenath Enterprises
Parasnath Township, Bldg-07, Wing-B, Type-G
possession by Dec 2028 · Shreenath Enterprises
Parijat Heights Building NO 3 Wing A
declared completion Jun 2026 · Viva Swastik Homes
Parivar Ashish Galaxy
possession by Jun 2029 · Parivar Ashish Developers
Parivar Complex Building NO 1 AND 3
possession by Jun 2030 · Parivar Homes
Parivar Complex Building NO 2
possession by Dec 2028 · Parivar Homes

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026