MahaRERA Property Intelligence · Thane

Parvati Nandan Co-operative Housing Society Limited

P51700032181 · Katemanivali · promoter Johnson Jesudas Nadar

Certificate SignedDue 31 May 2024

Delivery & Registration

MahaRERA registrationP51700032181
Registered on14 Dec 2021
Promoter-declared completion31 May 2024
Current statusCertificate Signed
Against todayabout 26 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
New Parvati Nandan1G+731 May 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Katemanivali, Hanuman Nagar, Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by Plot 40 Sanctioned LAyout, to the south by Plot 38 Sanctioned Layout, to the east by 15 Mtr DP Road and to the west by Remaining Area of S No 58 13F and Open Garden. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan East

Krishna Square
possession by Jul 2026 · Gopal Krishna Developers
SAI Heights
possession by Aug 2026 · Aaradhana Construction
Avighna Karan Wing C
possession by Aug 2026 · Avighna Karan
Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Durga Imperial
possession by Oct 2026 · G K Mali & C K Mali

Major developers building in Kalyan East

Other RERA-registered projects in Thane

Parvati Niwas
declared completion Dec 2025 · Aadarsh Developers
Parvati Park CO OP HSG SOC LTD
possession by Dec 2027 · Shreyas Enterprises AND Construction
Pataskar Eclat Building NO 3
declared completion Dec 2025 · Pataskar Developers Pvt. LTD
Patel Colossus Phase 1
declared completion Dec 2022 · Patel Group & Co
Patel Colossus Phase II
declared completion Dec 2023 · Patel Group & Co
Patel Colossus - Phase III
declared completion Dec 2023 · Patel Group & Co

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.