MahaRERA Property Intelligence · Thane

PRABHAKAR APARTMENT

P51700015374 · TITWALA · promoter Vaibhav Homes Developers

Certificate SignedDue 28 Dec 2020

Delivery & Registration

MahaRERA registrationP51700015374
Registered on20 Feb 2018
Promoter-declared completion28 Dec 2020
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vaibhav Homes Developers is the promoter of record on 60 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
PRABHAKAR APARTMENT1G+429 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 201928 Dec 2020DUE TO SCARCITY OF MATERIAL & LABOUR WE REQUEST FOR EXTENSION.

Location, Land & Connectivity

Located at TITWALA, RADHANAGAR, Kalyan, Thane, 421605. Per the filed land record, the plot is bounded to the north by 18 M WIDE DP ROAD, to the south by PLOT NO 91, to the east by 9 M WIDE ROAD and to the west by PLOT NO 105. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~39 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park39 km
Andheri MIDC / SEEPZ42 km
Chhatrapati Shivaji Int'l Airport45 km
Bandra Kurla Complex (BKC)46 km
Lower Parel / Worli business district54 km
Nariman Point / Fort60 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Titwala

Marathe Tower
possession by Jul 2026 · Saiji Developers
Marathe Elenza
possession by Jul 2026 · Saiji Developers
Ganpati Heights
possession by Sep 2026 · Manoj Prabhakar Patil
Indrayani
possession by Oct 2026 · Naresh Yashwant Patil
Mantra
possession by Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
possession by Nov 2026 · Rustagi Estates Private Limited

Other RERA-registered projects in Thane

Prabhakar Apartment
declared completion Jun 2019 · Shri Samartha Developer
Prabhat
declared completion Dec 2021 · Samay Homes
Prabhat Darshan
declared completion Dec 2025 · Yashomalhar Construction
Prabhu Ashish
declared completion Jun 2022 · Skyline Infrastructure
Prabhu Darshan CO-Operative Housing Society Limited
possession by Dec 2026 · NYP Developers
Prachi Residency
declared completion Dec 2024 · Prachi Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026