MahaRERA Property Intelligence · Thane

PRABHAT

P51700014178 · Bhaskar Colony · promoter Samay Homes

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP51700014178
Registered on13 Nov 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
PRABHAT1G+831 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202130 Jun 2021Extension due to Covid period lockdown and shortage of labour force at site. Extension is also sought due to delay in approvals from Thane Municipal Corporation due to first COVID

Location, Land & Connectivity

Located at Bhaskar Colony, Bhaskar Colony, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by Kuntewadi, to the south by Ashwamedh CHS, to the east by Deepashree CHS and to the west by Existing Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Naupada

Veer Galaxy
possession by Jul 2026 · Yash Infra
Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty

Major developers building in Naupada

Other RERA-registered projects in Thane

Prabhat Darshan
declared completion Dec 2025 · Yashomalhar Construction
Prabhu Ashish
declared completion Jun 2022 · Skyline Infrastructure
Prabhu Darshan CO-Operative Housing Society Limited
possession by Dec 2026 · NYP Developers
Prachi Residency
declared completion Dec 2024 · Prachi Developers
Pradeep CO-Operative Housing Society LTD
possession by Sep 2027 · Squarefeet Real Estate
Pradhan Mantri Awas Yojana - Urban
possession by Dec 2027 · Kulgaon Badlapur Municipal Council

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026