MahaRERA Property Intelligence · Thane

Veer Galaxy

P51700051438 · near vandana depo · promoter Yash Infra

Certificate SignedDue 30 Jul 2026

Delivery & Registration

MahaRERA registrationP51700051438
Registered on14 Jun 2023
Promoter-declared completion30 Jul 2026
Current statusCertificate Signed
Against today0 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~85.4% of the estimated project cost incurred as of the last certificate (₹14.75 Cr spent against a ₹17.27 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 42 homes filed with MahaRERA, 30 are sold/booked (22 with registered agreements + 8 booked) and 12 remain available (~71% sold) — selling steadily. Buyers have committed ₹21.86 Cr in agreement value so far. Of that, ₹12.86 Cr (~59%) is already collected, ₹9.00 Cr receivable — a read on how far along these sales really are. Note: the project registers 79 homes in total, but this sold/unsold inventory filing covers only 42 of them — the other 37 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 30 registered agreements, the effective carpet rate is ₹19,708/sqft (typical range ₹11,873–₹23,514) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1A-106838 sqft (77.85 sqm)₹1.19 Cr
Floor 1B-101514 sqft (47.75 sqm)₹63.65 Lakh
Floor 1B-102380 sqft (35.3 sqm)₹47.05 Lakh
Floor 1B-103205 sqft (19.04 sqm)₹25.38 Lakh
Floor 2A-201385 sqft (35.76 sqm)₹47.67 Lakh
Floor 2B-204406 sqft (37.71 sqm)₹50.27 Lakh
Floor 3B-304406 sqft (37.71 sqm)₹50.27 Lakh
Floor 4B-402380 sqft (35.3 sqm)₹47.05 Lakh
Floor 7A-701268 sqft (24.9 sqm)₹33.19 Lakh
Floor 7B-701514 sqft (47.75 sqm)₹63.65 Lakh
Floor 8B-804406 sqft (37.72 sqm)₹50.28 Lakh
Ground/Floor 0A-11149 sqft (13.84 sqm)₹31.15 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 79 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Veer Galaxy1G+779-

Unit mix on the filing: 63 residential and 16 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jul 202530 Jul 2026We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues

Location, Land & Connectivity

Located at near vandana depo, Ram Maruti road, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by Parimala chs, to the south by Ram maruti road, to the east by Mohan Mahal chs and to the west by Kamal chs. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yash Infra is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Yash Infra project & its RERA track record →

Other flagged projects by Yash Infra

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Veer Heights
possession by Apr 2028 · Veer Life Spaces LLP
Veer Hills
possession by Dec 2030 · Yash Infra
Veer Sapphire
possession by Sep 2029 · Veer Life Spaces LLP
Veer Vishwa
possession by Feb 2027 · Veer Life Spaces LLP
Veer Yashodeep
possession by Jan 2028 · Yash Infra
Veera Residency
declared completion May 2022 · Shree Ganesha Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026