MahaRERA Property Intelligence · Thane

PYRAMID ELEMENTS

P51700013897 · DIGHE · promoter Pyramid Infratech

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51700013897
Registered on30 Oct 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pyramid Infratech is the promoter of record on 176 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27.

BuildingWingsFloorsDeclared completion
PYRAMID ELEMENTS1G+2731 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at DIGHE, THANE BELAPUR ROAD, TTC IND. AREA, Thane, Thane, 400708. Per the filed land record, the plot is bounded to the north by ENCROACHMENT, to the south by 15 MTR ROAD, to the east by ENCROACHMENT AND PLOT NO P-130 and to the west by ENCROACHMENT. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park12 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pyramid Infratech CO is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Pyramid Infratech CO project & its RERA track record →

Other flagged projects by Pyramid Infratech CO

Pyramid Infratech CO
FlaggedThane

Other RERA-registered projects in Airoli

Shivesh Emerald
possession by Jul 2026 · Shivesh Realty Private Limited
Alliaance Galaxy
possession by Oct 2026 · Aashutosh Enterprise
Bramharaj Orchid
possession by Dec 2026 · Bramharaj Developers
ONE Pyramid
possession by Dec 2026 · Pacific Properties
Surbhi Sangeeta Co-Op. Housing Society Ltd
possession by Dec 2026 · Kumar & Kumar Builders LLP
Delta Luxuria
possession by Apr 2027 · Shreenathji Organisers PVT LTD

Major developers building in Airoli

Other RERA-registered projects in Thane

Pyramid Horizon
possession by Dec 2027 · Pyramid Construction
Pyramid Icon
declared completion Jun 2023 · Titanium Infracon
Q Islands R4
declared completion Dec 2024 · Aurum Realestate Developers Limited
Q Islands R5
declared completion Dec 2025 · Aurum Realestate Developers Limited
Q Islands R6
possession by Dec 2027 · Aurum Realestate Developers Limited
Q Islands R7
possession by Dec 2027 · Aurum Realestate Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026