MahaRERA Property Intelligence · Mumbai Suburban

RAHUL EXCELLENCE

P51700012698 · AMBARNATH · promoter Saroj Shrawankumar Bagaria

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700012698
Registered on07 Sep 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
RAHUL EXCELLENCE1G+4-

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002294726/01/2018Sandeep Jadhav vs Rahul Excellenceorder passed
CC00600000019618127/02/2021Udasi Enterprises Through Partner Mr Gorav Udasi vs Mrs. Saroj Shrawankumar Bagariaorder passed
CC00600000019646924/03/2021Udasi Enterprises Through Partner Mr Raj Udasi vs Mrs. Saroj Shrawankumar Bagariaorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court133 OF 20172017Pending
Bombay High Court178 OF 20172017Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202231 Dec 2021The Project was completed in December 2018 and application for Occupation Certificate has been made to the concerned authority in February 2019. However, till date Occupation Certi

Location, Land & Connectivity

Located at AMBARNATH, PLOT NO 9 AND 10, Ulhasnagar, Thane, 421501. Per the filed land record, the plot is bounded to the north by GUT NO 10 CTS NO 9285, to the south by 25 FEET INTERNAL ROAD OF GUT NO 11, to the east by PLOT NO 7 AND 8 OF GUT NO 11 and to the west by 60 FEET DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park31 km
Andheri MIDC / SEEPZ34 km
Chhatrapati Shivaji Int'l Airport36 km
Bandra Kurla Complex (BKC)36 km
Lower Parel / Worli business district43 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

24 High Bizbay
possession by Jul 2026 · Apex Infra
Shree Gajanan Enterprises Rukhmini CHS
possession by Jul 2026 · Shree Gajanan Enterprises Rukhmini CHS
Walekar Homes
possession by Aug 2026 · Walekar & Son's Developers
Patels Eirene
possession by Aug 2026 · Pramukh Developers
Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters

Major developers building in Ambernath

Other RERA-registered projects in Thane

RAI Paradise
declared completion Dec 2018 · RAI Residency Private Limited
Rai S Aaragya
possession by Dec 2026 · RAI Residency Private Limited
RAI S Galaxy
possession by Dec 2029 · RAI Residency Private Limited
Rai S Heaven
possession by Dec 2026 · RAI Residency Private Limited
RAI S Heritage D Wing
declared completion Dec 2018 · RAI Residency Private Limited
RAI S Nisarg
declared completion Dec 2025 · RAI Residency Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026