MahaRERA Property Intelligence · Mumbai Suburban

RAJ DARSHAN

P51800018351 · ANDHERI EAST · promoter Venezia Realtors

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP51800018351
Registered on24 Oct 2018
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
RAJ DARSHAN1G+10-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000020961420/01/2022Mr Neelesh Jha and Mrs Tricia Jha vs M/s Venezia Realtorsorder passed

Legal & Litigation

The promoter has declared 12 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Dinodoshi33032016For Hearing
City Civil Dinodoshi33042016For Hearing
City Civil Dinodoshi13562018Consent Terms Filed
City Civil Dinodoshi11172022For Hearing
City Civil Dinodoshi4342023For Hearing
High Court32462019Disposed
High Court4752020For Admission
High Court5362020For Admission
Small Causes Court Bandra1052010Disposed
Small Causes Court Bandra1062010Disposed
Small Causes Court Bandra22017For Hearing
Small Causes Court Bandra12017For Hearing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202131 Dec 2023Covid-19

Location, Land & Connectivity

Located at ANDHERI EAST, ANDHERI KURLA ROAD, Mumbai City, Mumbai City, 400059. Per the filed land record, the plot is bounded to the north by CTS NO 1377 AND 1378OF VILLAGE MAROL, to the south by CTS NO 1374 OF VILLAGE MAROL, to the east by CTS NO 1374 OF MAROL and to the west by CHURCH ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri East

Royal Green
possession by Dec 2026 · Admire Revive Builder & Developer
VKG Estates
possession by Dec 2026 · Greenery Rock LLP
59 Avenue
possession by Dec 2026 · M/s Ganesh Vishal Infra Engineering Priv
Gateway Residences
possession by Dec 2026 · Infinity Narayani Associates
LA Grace
possession by Dec 2026 · Ecohomes Ventures
Park Royale Phase III
possession by Dec 2026 · Shivranjani Properties LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

RAJ Ekjyot Sukruti
declared completion Dec 2018 · Sadguna Realty
RAJ Imperia
possession by Oct 2027 · RAJ Corp
Raj Nirman
declared completion Jun 2018 · Ferro Build
RAJ ONE
possession by Aug 2027 · RAJ Realtors
RAJ Pantheon
declared completion Dec 2025 · Not Available
RAJ Rani Pride
declared completion Dec 2022 · Geetaraj Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026