MahaRERA Property Intelligence · Mumbai Suburban

Rajhans Helix 3

P51800007413 · Ghatkopar West · promoter Rajhans Infracon (India)

Certificate SignedDue 31 Aug 2023

Delivery & Registration

MahaRERA registrationP51800007413
Registered on17 Aug 2017
Promoter-declared completion31 Aug 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rajhans Infracon (India) is the promoter of record on 189 projects, of which 18 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Rajhans Helix 31G+1231 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Aug 202331 Aug 2023We have already obtained all floor major area Occupation Certificate except 10 units on rear side of project for 5th to 8th floor pending. We have completed construction 100% and a
31 Aug 202330 Dec 2020The Application for approval for the 3 Basement Plus 8 Upper floor was made in July 2017 with completion date as 31.12.2019 in anticipation of that DCPR 2034 will be published and
31 Aug 202330 Jun 2022We have face difficulty in some complex cinema approval as per DCPR 2034 in the proposed building. Due to 1st lockdown which affect material and labour supply largely and again due

Location, Land & Connectivity

Located at Ghatkopar West, LBS Marg, Andheri, Mumbai Suburban, 400086. Per the filed land record, the plot is bounded to the north by Property CTS No 2265 Part, to the south by 13 40 mtr Sanghani Estate Road, to the east by L B S Marg and to the west by 9 20 mtr Sanghani Estate Scheme Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)5 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar West

Kesar Leor
possession by Aug 2026 · M S Realtors
Sarvodaya Heights
possession by Sep 2026 · CMG Enterprises
O AND S Royale
possession by Dec 2026 · Suchita Orange Project Royale
Sarvonnati CHS LTD
possession by Dec 2026 · JAI Enterprises
Vighneshwar Cooperative Housing Society Limited
possession by Dec 2026 · Vighneshwar Coop Housing Society Limited
Arihant Heights
possession by Dec 2026 · Arihant Infrastructure Company

Other RERA-registered projects in Mumbai Suburban

Rajhans Solitaire
possession by Aug 2026 · Rajhans Residency
Rajhans Splendid
declared completion Dec 2024 · Rajhans Reality
Rajhans Vandana
possession by Dec 2027 · Rajhans Constructions
Rajinfinia Phase II Wing A Wing B Wing C
declared completion Dec 2024 · Rajsanket Realty Limited
Rajita Villa
declared completion Feb 2024 · Siddharth Enterprises
Rajkamal
declared completion Nov 2021 · RAJ Constructions

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026